Contract award notice

Information

Published

Date of dispatch of this notice: 18/07/2022

External Reference: 2022-270915

TED Reference: 2022/S 140-398149

Contract award notice

[NoticeContractAward]

[NoticeContractAwardSub]

[Directive201424]

[Section1]: [Ca]

I.1)

[NameAddressContact]

Irish Defence Forces
N/A
McKee Barracks
Dublin 7.
Blackhorse Ave.
IE
[Contactpoint]: Louise Fitzsimons
[Nutscode]:  IE -  IRELAND
[Internets]:
I.4)

[CaType]

[MaintypeMinistry]
I.5)

[Mainactivity]

[MainactivDefence]

[Section2]: [Object]

II.1)

[QuantityScopeContract]

II.1.1)

[TitleContract]

A Lightweight Modular General Support Bridge
[Fileref]:  DE-66-22
II.1.2)

[CpvMain]

34144300  - 
II.1.3)

[TypeContract]

[Supplies]
II.1.4)

[DescrShort]

In summary, the Goods comprise: The Corps of Engineers are seeking the provision of a lightweight modular military general support bridge to provide a general support bridging capability to the Defence Forces. The bridge must have a span no less than 30m and no more than of 35m across a wet or dry gap with an MLC of 70T. The bridge system must provide a roadway width of 4m with parapet/handrails. The option of segregated walkway with handrails can also be priced. The bridge comprises of a girder bridge system made up from light alloy components to comprise each bay. The largest component will be a maximum of a 6 man lift (<=290kg). The average component will be a maximum of a 4 man lift (<=195kg).
II.1.6)

[LotsInfo]

[DivisionLots]: [No]
II.1.7)

[ValueTotal]

[ValueExclVat]:  2869119.00  EUR
II.2)

[Description]

II.2.2)

[CpvAdditional]

42414220  - 
44212100  - 
II.2.3)

[PlacePerformance]

[Nutscode]:  IE -  IRELAND
[MainsiteplaceWorksDelivery]:  
Curragh Camp Co Kildare
II.2.4)

[DescrProcurement]

In summary, the Goods comprise: The Corps of Engineers are seeking the provision of a lightweight modular military general support bridge to provide a general support bridging capability to the Defence Forces. The bridge must have a span no less than 30m and no more than of 35m across a wet or dry gap with an MLC of 70T. The bridge system must provide a roadway width of 4m with parapet/handrails. The option of segregated walkway with handrails can also be priced. The bridge comprises of a girder bridge system made up from light alloy components to comprise each bay. The largest component will be a maximum of a 6 man lift (<=290kg). The average component will be a maximum of a 4 man lift (<=195kg).
II.2.5)

[AwardCriteria]

[AwardCriteriaBelow]
[Price]
II.2.11)

[OptionsInfo]

[Options]: [No]
II.2.13)

[EuProgrInfo]

[EuProgrRelated]: [No]

[Section4]: [Procedure]

IV.1)

[Description]

IV.1.1)

[TypeProcedure]

[ProctypeOpen]
IV.1.8)

[GpaInfo]

[GpaCovered] : [Yes]
IV.2)

[InfoAdmin]

IV.2.1)

[PubPrevious]

[NumberOj]: 2022/S 070-182938

[Section5]: [AwardOfContract]

[ContractNumber]: 1

[TitleContract]: A Lightweight Modular General Support Bridge

[AwardConfirm]: [Yes]
V.2)

[AwardOfContract]

V.2.1)

[DateAward]

15/07/2022
V.2.2)

[AwardOffersInfo]

[OffersReceived]:  1
[AwardedGroup] :  [No]
V.2.3)

[AwardedToName]

WFEL Ltd
Sir Richard Fairey Road
Stockport, Chesire
SK45DY
UK
[Nutscode]:  UK -  UNITED KINGDOM

[AwardedSme] : [Yes]
V.2.4)

[ValueContractInfo] ([ExclVat])

[ValueTotalFinal]:  2869119.00  EUR

[Section6]: [InfoComplement]

VI.4)

[AppealsProcedure]

VI.4.1)

[AppealsBody]

High Court of Ireland
Inns Quay
Dublin
1
IE