II.1)
[QuantityScopeContract]
Reserved Specialists (Electrical Contractors) for the Construction of a new special school for Rosedale School at Woodlands Centre, Renmore, Galway
[Fileref]:
20070J
[Works]
Construction of a new c.3,640 sq.m. single storey special school for Rosedale School on a greenfield site at the Woodlands Centre, Renmore, Galway. The works also include construction of a 39 sq.m. single storey ancillary storage shed; all associated site development works including works to the existing Woodlands campus entrance, revised access road, staff and visitor car parking, bus drop-off areas, new perimeter boundary walls and fences, removal of selected trees and new ancillary site signage; and all associated site services including surface and foul water drainage rainwater harvesting system, underground rainwater tanks and site lighting.
Reserved Specialist’s role: Electrical reserved specialists roles shall consist of installation, testing and commissionining of all electrical installations including sub-specialists works associated with the works.
II.1.5)
[ValueMagnitudeEstimatedTotal]
[ValueExclVat]: 1100000.00
EUR
[DivisionLots]:
[No]
II.2.3)
[PlacePerformance]
[MainsiteplaceWorksDelivery]:
Galway
II.2.4)
[DescrProcurement]
Construction of a new c.3,640 sq.m. single storey special school for Rosedale School on a greenfield site at the Woodlands Centre, Renmore, Galway. The works also include construction of a 39 sq.m. single storey ancillary storage shed; all associated site development works including works to the existing Woodlands campus entrance, revised access road, staff and visitor car parking, bus drop-off areas, new perimeter boundary walls and fences, removal of selected trees and new ancillary site signage; and all associated site services including surface and foul water drainage rainwater harvesting system, underground rainwater tanks and site lighting.
Reserved Specialist’s role: Electrical reserved specialists roles shall consist of installation, testing and commissionining of all electrical installations including sub-specialists works associated with the works.
Reserved Specialists are being pre-selected and procured separately from the Main Contract and when procured will enter into contract with the Main Contractor.
[AwardCriteriaDescriptive]
II.2.6)
[ValueMagnitudeEstimated]
[ValueExclVat]: 1100000.00
EUR
II.2.7)
[DurationContractFrameworkDps]
[DurationMonths]:
18
[RenewalsSubject]:
[No]
[EnvisagedNumber]:
8
[CriteriaChoosingLimited]:
As Suitability Assessment Questionnaire.
[VariantsAccepted]:
[No]
[Options]:
[No]
[EuProgrRelated]:
[No]
II.2.14)
[InfoAdditional]
Reserved Specialists are being pre-selected and procured separately from the Main Contract and when procured will enter into contract with the Main Contractor. Reserved Specialists will be required to execute a Collateral Warranty with the Employer.