The N51 Dunmoe Phase 2 Realignment Scheme
Reference number:
MH-TRA-21-01
45233120
-
Road construction works
Works
II.1.4)
Short description
The N51 Dunmoe Phase 2 Realignment Scheme comprises the construction of 4.375km of Type 1 Single Carriageway (S2) and the following associated works:
• At grade junctions and links to existing road network
• Surface water drainage infrastructure.
• Underbridge at Cruicetown Stream
• Underpass
• Retaining Wall
• Culverts and associated headwalls
• Utility diversions and ducting for utilities including ESB, Eir and Watermains.
• Road signs, road markings and road studs.
• Site clearance and earthworks
• Boundary treatment works and Accommodation Works
• Landscaping works
• Road pavements
The contractor will be required to produce Traffic Management plans for the N51 National Secondary road and local roads. The contractor will also be appointed as the Project Supervisor Construction Stage (PSCS).
II.1.6)
Information about lots
This contract is divided into lots:
no
II.1.7)
Total value of the procurement
Value excluding VAT:
10927359.35
EUR
II.2.2)
Additional CPV code(s)
45200000
-
Works for complete or part construction and civil engineering work
45230000
-
Construction work for pipelines, communication and power lines, for highways, roads, airfields and railways; flatwork
45233000
-
Construction, foundation and surface works for highways, roads
45233100
-
Construction work for highways, roads
II.2.3)
Place of performance
NUTS code:
IE062 -
Mid-East
II.2.4)
Description of the procurement
The N51 Dunmoe Phase 2 Realignment Scheme comprises the construction of 4.375km of Type 1 Single Carriageway (S2) and the following associated works:
• At grade junctions and links to existing road network
• Surface water drainage infrastructure.
• Underbridge at Cruicetown Stream
• Underpass
• Retaining Wall
• Culverts and associated headwalls
• Utility diversions and ducting for utilities including ESB, Eir and Watermains.
• Road signs, road markings and road studs.
• Site clearance and earthworks
• Boundary treatment works and Accommodation Works
• Landscaping works
• Road pavements
The contractor will be required to produce Traffic Management plans for the N51 National Secondary road and local roads. The contractor will also be appointed as the Project Supervisor Construction Stage (PSCS).
II.2.11)
Information about options
Options:
no
II.2.13)
Information about European Union funds
The procurement is related to a project and/or programme financed by European Union funds:
no