Corrigendum

Information

Published

Date of dispatch of this notice: 16/11/2021

External Reference: 2021-223311

TED Reference: 2021/S 225-593657

Corrigendum

[NoticeCorrigendum]

[NoticeCorrigendumSub]

[Services]

[Directive201425]

[Section1]: [CaCe]

I.1)

[NameAddressContact]

EirGrid plc
N/A
Block 2 - The Oval, 160 Shelbourne Road
Ballsbridge
D04 FW28
IE
[Contactpoint]: Keith Doherty
[Nutscode]:  IE -  IRELAND
[Internets]:

[Section2]: [Object]

II.1)

[QuantityScopeContract]

II.1.1)

[TitleContract]

Requirement for Temporary Emergency Generation - 200MW
[Fileref]:  ENQEIR778
II.1.2)

[CpvMain]

51112100  - 
II.1.3)

[TypeContract]

[Services]
II.1.4)

[DescrShort]

The CRU, with the consent of the Minister for the Environment, Climate and Communications, has directed EirGrid under Regulation 28(10) of the Regulations, in our capacity as the transmission system operator, to secure the delivery of c. 200MW of emergency temporary generation from 2022
EirGrid is therefore seeking a Candidate(s) that can provide 200 MW of generation onto the transmission network by a target date of Q3 2022. (The provision of the fully operational generation is required for 3 years from this date)

[Section6]: [InfoComplement]

VI.6)

[IcarOriginalRef]

[NumberOj]: 2021/S 201-525928

[Section7]: [Changes]

VII.1)

[IcarCorrectAdd]

VII.1.2)

[IcarTextCorrected]

[SectionNo]:  IV.2.2
[IcarInstead]:  
[Date]:  15/11/2021
[Time]:  13:00
[IcarRead]:  
[Date]:  16/11/2021
[Time]:  13:00