II.1)
[QuantityScopeContract]
Relocation of Audiology, Orthodontics & Ophthalmology departments to St. Otteran's Campus, Waterford. - Mechanical Contractor
[Fileref]:
EST-Mech
[Works]
Relocation of the Audiology, Orthodontics & Ophthalmology departments from University Hospital Waterford to St. Otteran's Campus, Upper Grange Road, Waterford.
II.1.5)
[ValueMagnitudeEstimatedTotal]
[ValueExclVat]: 5500000.00
EUR
[DivisionLots]:
[No]
45210000
-
45215100
-
51100000
-
51120000
-
II.2.3)
[PlacePerformance]
II.2.4)
[DescrProcurement]
Relocation of the Audiology, Orthodontics & Ophthalmology departments from University Hospital Waterford to St. Otteran's Campus, Upper Grange Road, Waterford.
[AwardCriteriaDescriptive]
II.2.6)
[ValueMagnitudeEstimated]
[ValueExclVat]: 5500000.00
EUR
II.2.7)
[DurationContractFrameworkDps]
[DurationMonths]:
15
[RenewalsSubject]:
[No]
[VariantsAccepted]:
[No]
[Options]:
[No]
[EuProgrRelated]:
[No]