[MainsiteplaceWorksDelivery]:
Dublin
Iarnród Éireann-Irish Rail "IE" has a requirement for a multi-disciplinary Consultancy team to support IE in the proposed expansion of the Dublin Area Rapid Transit network "DART". This requirement is for a team to support the proposed expansion of the Kildare Line including but not limited to:
*Preparation of designs
*Undertake environmental impact assessment
*Manage the Railway order process
*Tender preparation and evaluation
*With an option for design support during construction stage
[AwardCriteriaBelow]
[AwardCriterionQuality]
-
[AwardCriterionName]:
Proposed Project team
/
[Weighting]:
15%
[AwardCriterionQuality]
-
[AwardCriterionName]:
Proposed methodology for design - Railway electrification
/
[Weighting]:
2%
[AwardCriterionQuality]
-
[AwardCriterionName]:
Proposed methodology for design - Railway Signalling
/
[Weighting]:
2%
[AwardCriterionQuality]
-
[AwardCriterionName]:
Proposed methodology for design - Railway Telecommunications
/
[Weighting]:
2%
[AwardCriterionQuality]
-
[AwardCriterionName]:
Proposed methodology for design - Railway Railway & road Civil engineering features & structures
/
[Weighting]:
2%
[AwardCriterionQuality]
-
[AwardCriterionName]:
Proposed methodology for design - Railway Station design Architecture & Building
/
[Weighting]:
2%
[AwardCriterionQuality]
-
[AwardCriterionName]:
How the approach to design for the above elements can be implemented to ensure minimum disruption to operational train services
/
[Weighting]:
4%
[AwardCriterionQuality]
-
[AwardCriterionName]:
Proposed methodology for the management of the Railway Order process
/
[Weighting]:
10%
[AwardCriterionQuality]
-
[AwardCriterionName]:
Proposed methodology for cost management
/
[Weighting]:
2%
[AwardCriterionQuality]
-
[AwardCriterionName]:
Identify critical issues in forming a procurement strategy for the delivery of the works
/
[Weighting]:
2%
[AwardCriterionQuality]
-
[AwardCriterionName]:
- Proposed MDC Delivery Programme
/
[Weighting]:
3%
[AwardCriterionQuality]
-
[AwardCriterionName]:
Proposed MDC Corporate Governance Systems
/
[Weighting]:
2%
[AwardCriterionQuality]
-
[AwardCriterionName]:
Proposed methodology for the provision of Design Support during the Construction Phase
/
[Weighting]:
2%
[AwardLowestCost]
-
[AwardCriterionName]:
Cost
/
[Weighting]:
50%
[Options]:
[Yes]
[OptionsDescr]:
The Contract the subject of this competition is a contract for approximately 2 years with an option to extend for the duration of the project, subject to the terms and conditions of the Contract