II.1)
[QuantityScopeContract]
Academic Hub Library Complex
[Fileref]:
09AHLC
[Works]
The initial phase of the TU Dublin Academic Hub & Library Complex is planned as a cluster of buildings and courtyards, both existing and new around the historic North House protected structure. The library and student support complex will sit at the heart of the new Grangegorman campus, addressing a large plaza and commanding views over the city.
The overall Phase 1 development is approximately 12,580m2 in area. The development consists of 9,505m2 of New Build construction with the balance comprising the retained elements of the North House East and North House West protected structures (Planning Ref GSDZ2346/19).
The scope of works will include the demolition of existing redundant structures including the stand alone North House Annexe, Changing Rooms and extensions to the existing North House buildings. The GDA is seeking to shortlist the top 5 ranking main contractors and top 5 ranking reserved specialist subcontractors
II.1.5)
[ValueMagnitudeEstimatedTotal]
[ValueExclVat]: 50000000.00
EUR
[DivisionLots]:
[No]
39000000
-
42416100
-
44900000
-
45210000
-
45214400
-
45262510
-
45262650
-
45300000
-
45310000
-
45350000
-
45351000
-
45441000
-
45443000
-
II.2.3)
[PlacePerformance]
[MainsiteplaceWorksDelivery]:
Dublin
II.2.4)
[DescrProcurement]
The initial phase of the TU Dublin Academic Hub & Library Complex is planned as a cluster of buildings and courtyards, both existing and new around the historic North House protected structure. The library and student support complex will sit at the heart of the new Grangegorman campus, addressing a large plaza and commanding views over the city.
The overall Phase 1 development is approximately 12,580m2 in area. The development consists of 9,505m2 of New Build construction with the balance comprising the retained elements of the North House East and North House West protected structures (Planning Ref GSDZ2346/19).
The scope of works will include the demolition of existing redundant structures including the stand alone North House Annexe, Changing Rooms and extensions to the existing North House buildings. The GDA is seeking to shortlist the top 5 ranking main contractors and top 5 ranking reserved specialist subcontractors
[AwardCriteriaDescriptive]
II.2.6)
[ValueMagnitudeEstimated]
[ValueExclVat]: 50000000.00
EUR
II.2.7)
[DurationContractFrameworkDps]
[DurationMonths]:
23
[RenewalsSubject]:
[No]
[EnvisagedNumber]:
6
[VariantsAccepted]:
[No]
[Options]:
[No]
[EuProgrRelated]:
[No]