II.1)
Scope of the procurement
Wind and Solar Power Forecasting
Reference number:
ENQEIR652
71351600
-
Weather-forecasting services
Services
II.1.4)
Short description
This tender is complete.
The Scope of Requirements is expected to include, but is not limited to:
• Provide short term wind and solar power forecasts, every 15 minutes for each wind and solar farm in Ireland and Northern Ireland.
• Provide multiple long term wind and solar power forecasts per day up to 5 days ahead for each wind and solar farm in Ireland and Northern Ireland.
• Provide confidence bands for each of the forecasts provided.
• Provide wind and solar power ramping forecasts
• Receive and transmit data in real time using existing EirGrid infrastructure.
EirGrid envisages qualifying up to seven Candidates from this pre-qualification process, subject to the quality of responses received.
II.1.6)
Information about lots
This contract is divided into lots:
no
II.1.7)
Total value of the procurement
( Agree to publish? yes )
Value excluding VAT:
1800000.00
EUR
II.2.2)
Additional CPV code(s)
71351600
-
Weather-forecasting services
II.2.4)
Description of the procurement
This tender process is complete.
EirGrid is looking to establish a multi-party Framework consisting of two separate companies who are required to provide Wind and Solar Power Forecasting Services.
As transmission system operators, the EirGrid Group are responsible for managing electricity demand and supply balance on the transmission system. There is currently over 4700 MW of wind power generation and 138 MW of solar PV generation installed on the system and, at times, the output from renewables has represented more than 65% of the instantaneous demand for electricity. The amount of wind and solar power generation connected to our system continues to increase, with at least an additional 1000 MW expected to connect by the end of 2020 and further growth expected in the following years.
Wind and solar power forecasting serves as an integral tool to manage this ever increasing portfolio of variable generation which enables efficient and reliable operation of the power system. Wind and solar power forecasting is used for various purposes across multiple forecasting horizons within the organisation.
The accuracy of the wind and solar power forecasts are integral to our operational planning, and scheduling and dispatch. To meet this end a component of the payment for provision of wind and solar power forecasting services will be based on the accuracy of the forecasts. The reliability and delivery of an accurate wind power forecast enables us to manage the power system securely, safely and economically.
II.2.5)
Award criteria
( Agree to publish? yes )
Criteria below
Quality criterion
-
Name:
Incentivisation
/
Weighting:
0
Quality criterion
-
Name:
Fitness for Purpose
/
Weighting:
50
Quality criterion
-
Name:
Data Exchange Implementation
/
Weighting:
5
Quality criterion
-
Name:
Contract Management
/
Weighting:
10
Quality criterion
-
Name:
Legal
/
Weighting:
5
Price
-
Weighting:
30
II.2.11)
Information about options
Options:
yes
Description of options:
The Framework Agreement period will be for an initial duration of four years with the option to extend annually for up to an additional four years, subject always to the satisfactory performance of the suppliers.
II.2.13)
Information about European Union funds
The procurement is related to a project and/or programme financed by European Union funds:
no
II.2.14)
Additional information
The estimate contract value of €1,800,000 is taking into account the contract being extended for the additional 4 years.