Contract award notice - utilities

Information

Published

Date of dispatch of this notice: 06/11/2018

External Reference: 2018-226966

TED Reference: 2018/S 216-495050

Contract award notice - utilities

[NoticeAwardUtilities]

[NoticeContractAwardSub]

[Services]

[Directive201425]

[Section1]: [Ce]

I.1)

[NameAddressContact]

Iarnrod Eireann-Irish Rail
N/A
Procurement, CIE Works,
Dublin 8
Inchicore
IE
[Contactpoint]: Tommy Conlon
[AddressPhone]: +353 017033539
[Internets]:
[UrlGeneral]: www.irishrail.ie

I.6)

[Mainactivity]

[MainactivRailway]

[Section2]: [Object]

II.1)

[QuantityScopeContract]

II.1.1)

[TitleContract]

Project Management and Support Services for IE’s National Train Control Centre and Traffic Management System (TMS).
[Fileref]:  7114
II.1.2)

[CpvMain]

72224000  - 
II.1.3)

[TypeContract]

[Services]
II.1.4)

[DescrShort]

IÉ is seeking to engage an external project management Consultant to provide support for two areas:
A. Safety Assurance & Integration Services.
B. Administration of the NEC 3, Option C Target Cost TMS contract.
Further information contained within the attached PQQ.
II.1.6)

[LotsInfo]

[DivisionLots]: [No]
II.2)

[Description]

II.2.2)

[CpvAdditional]

72220000  - 
II.2.4)

[DescrProcurement]

IÉ is seeking to engage an external project management Consultant to provide support for two areas:
A. Safety Assurance & Integration Services.
B. Administration of the NEC 3, Option C Target Cost TMS contract.
Further information contained within the attached PQQ.
II.2.11)

[OptionsInfo]

[Options]: [Yes]
[OptionsDescr]:
Reserve the right to extend the contract until the completion of the project.
II.2.13)

[EuProgrInfo]

[EuProgrRelated]: [No]

[Section4]: [Procedure]

IV.1)

[Description]

IV.1.1)

[TypeProcedure]

[ProctypeNegotWCall]
IV.1.8)

[GpaInfo]

[GpaCovered] : [No]
IV.2)

[InfoAdmin]

IV.2.1)

[PubPrevious]

[NumberOj]: 2018/S 174-395695

[Section5]: [AwardOfContract]

[ContractNumber]: 7114

[TitleContract]: Project Management and Support Services for IE’s National Train Control Centre and Traffic Management System (TMS).

[AwardConfirm]: [No]
V.1)

[AwardNoawardInfo]

[AwardNoaward]
[AwardNoTenders]

[Section6]: [InfoComplement]

VI.3)

[InfoAdditional]

The Contract Award will be in two stages. Stage 1 will consist of the engagement of the SAM and SI who will be required to assit IÉ in all aspects of the CRR approval process. If CRR Approval is granted then Stage Two consists of the award the contract in its entirety. The Contract in its entirety cannot be awarded in the absence of the CRR approval. Economic Operators should also be aware that a break between stages 1 & 2 may be required.
VI.4)

[AppealsProcedure]

VI.4.1)

[AppealsBody]

The High Court
Dublin