The project includes the Replacement of 2 no. MTHW Boilers with 3 No. MTHW Boilers. The contractor will be responsible for the installation of associated boiler plant including pressuiration equipment, Heat exchangers, circulating pumps, valves, pipework & insulation. The exisitng boiler flues & a solid fuel hopper installation are to be demolished on site. A free standing flue will be installed on a new concrete plinth to the rear of the boiler house. The boiler house will be extensively renovated to accomodate the proposed new boiler plant & equipment. Builders works is required including construction & fitting out of the renovated boiler house, roof alterations to accomodate the new flue installation, & works associated with a bunded oil storage compound. Electrical Works include replacement cabling, local isolators for boiler plant, emergency lighting & fire alarm works. The BMS in the boiler house is to be updated & new boiler house panels are to be installed. The works require phasing of shutdowns of old equipment and changeovers to new equipment. Close Integration will be required with the maintenance department in the hospital. Main contract works include management & co-ordination of M&E works, health & safety co-ordination & interaction with Hospital Maintenance to procure the works in an acceptable phased manner to ensure no interruption of hospital services.
Works
24/03/2017 12:00:00
42160000-8 Boiler installations
45000000-7 Construction work
45215100-8 Construction work for buildings relating to health
45310000-3 Electrical installation work
45317000-2 Other electrical installation work
45331000-6 Heating, ventilation and air-conditioning installation work
45350000-5 Mechanical installations
45453100-8 Refurbishment work
Health Service Executive (HSE)
Head Office
Millennium Park
Naas
Ireland
[ViewProfile]
Feargal McGirl
http://www.hse.ie
Notice | [DispatchDate] |
---|---|
Contract Notice (eTenders) | 22/12/2016 13:00 |
Contract Award Notice (eTenders) | 01/02/2018 15:55 |
Sligo Unversity Hospital - Boiler Plant Replacement Main Contractor
Please complete attached Suitability assessment questionnaire as HSE Estates NW intends to create a shortlist of 5 to 8 qualified contractors who will be invited to submit tenders for the Replacement of 2 No. MTHW Boilers with 3 No. MTHW Boilers. They will be responsible for the installation of associated boiler plant including pressurisation equipment, Heat exchangers, circulating pumps, valves, pipework,insulation & associated works.
Sligo Unversity Hospital - Boiler Plant Replacement Electrical Contractor - Lot 2
Please complete attached Suitability assessment questionnaire as HSE Estates NW intends to create a shortlist of 5 to 8 qualified contractors who will be invited to submit tenders for the Replacement of 2 no. MTHW Boilers with 3 No. MTHW Boilers. They will be responsible for the installation of associated boiler plant including pressurisation equipment, Heat exchangers, circulating pumps, valves, pipework,insulation & associated works.
Sligo Unversity Hospital - Boiler Plant Replacement Mechanical Contractor Lot 3
Please complete attached Suitability assessment questionnaire as HSE Estates NW intends to create a shortlist of 5 to 8 qualified contractors who will be invited to submit tenders for the Replacement of 2 No. MTHW Boilers with 3 No. MTHW Boilers. They will be responsible for the installation of associated boiler plant including pressurisation equipment, Heat exchangers, circulating pumps, valves, pipework,insulation & associated works.