II.1)
Scope of the procurement
Civil Balance of Plant (CBOP) Contract for Oweninny Phase 2 Wind Farm
Reference number:
GWM-11136
45200000
-
Works for complete or part construction and civil engineering work
Works
II.1.4)
Short description
Oweninny Power 2 DAC, the Contracting Entity , is a joint venture company formed between Bord na Móna Energy Ltd and ESB Wind Development Ltd. Oweninny Power DAC has developed the first phase of a Wind Farm at Oweninny, Bellacorick, Co. Mayo. The Contracting Entity now intends to procure works, supplies and services related to civil balance of plant for the Oweninny Phase 2 wind farm project.
Oweninny Phase 2 wind farm is an 83MW project located adjacent to the existing 89MW Oweninny Phase 1 Project. The Contracting Entity plans to develop the phase 2 project commencing in 2020.
II.1.6)
Information about lots
This contract is divided into lots:
no
II.2.2)
Additional CPV code(s)
71322000
-
Engineering design services for the construction of civil engineering works
II.2.3)
Place of performance
Main site or place of performance:
Oweninny Wind Farm, Co. Mayo, Ireland
II.2.4)
Description of the procurement
The Contracting Entity intends to procure works, supplies and services related to civil balance of plant for the Oweninny Phase 2 wind farm project.
The scope of work for Contract shall include the design, procurement and installation for the following non-exhaustive list, however tenders should note that the detailed scope and contracting strategy will be determined at tender stage:
1. Site Accommodation for the Employer & Engineer
2. Fulfilling the role of PSCS during all or part of the Works, which may include other parties on site (e.g. Wind Turbine Generator (WTG) Erection & Electrical Balance of Plant (EBOP) contracts
3. Pre-construction surveys
4. Enabling Works
5. Discharge of Planning Conditions
6. Onsite access tracks
7. Stream Crossings
8. Drainage Works
9. Site compounds grading and fencing for the WTG erection and EBOP contractors
10. Public road modifications to facilitate delivery of abnormal loads from the Port to Site
11. On site & offsite scrub clearance/tree felling
12. WTG Foundations & crane hardstandings
13. Civil works attendance on other contractors on site
14. Met mast procurement and erection, including foundation and crane hardstanding
15. Reinstatement
16. Route modifications along haul route to facilitate WTG transportation and subsequent reinstatement works
17. Environmental monitoring and reporting including dust noise and water quality during the construction phase
Some post construction works/services during the project operational phase may also be included in the scope of the Contract.
II.2.11)
Information about options
Options:
no
II.2.13)
Information about European Union funds
The procurement is related to a project and/or programme financed by European Union funds:
no
II.2.14)
Additional information
It is currently envisaged that the Contracting Entity shall enter into a Contract with the successful tenderer. However, Applicants should note that, in the alternative, the Contract may ultimately be entered into by any subsidiary or affiliate thereof, or by either of the shareholders in the Contracting Entity.