II.1)
Scope of the procurement
Overhead Line Construction for North-South 400 kV Interconnector under a multi-contractor Framework Agreement
Reference number:
D20/CON/864
45232210
-
Overhead line construction
Works
II.1.4)
Short description
Electricity Supply Board (ESB) proposes procuring a multi-contractor Framework Agreement for the installation of a North-South 400 kV overhead line. ESB is undertaking the procurement of the framework agreement on behalf of itself for works in the Republic of Ireland (ROI) and on behalf of Northern Ireland Electricity Networks Limited (NIE Networks) for works in Northern Ireland (NI) and is the Contracting Entity for the purposes of this Procurement. The successful Contractors to this Framework Agreement should be willing to undertake works in Northern Ireland on behalf of NIE Networks and in the Republic of Ireland on behalf on ESB. The multi-contractor Framework Agreement will involve the construction of a single circuit 400 kV overhead transmission line supported by circa 401 towers for a distance of circa 140 km from a new NIE Networks substation at Turleenan, Co. Tyrone to the existing ESB substation in Woodland, Co Meath.
II.1.6)
Information about lots
This contract is divided into lots:
no
II.2.2)
Additional CPV code(s)
31321100
-
Overhead power lines
31682410
-
Overhead cable carriers
44212200
-
Towers, lattice masts, derricks and pylons
44212230
-
Towers
II.2.3)
Place of performance
NUTS code:
UKN -
NORTHERN IRELAND
NUTS code:
IE -
IRELAND
II.2.4)
Description of the procurement
Electricity Supply Board (ESB) proposes procuring a multi-contractor Framework Agreement for the installation of a North-South 400 kV overhead line. ESB is undertaking the procurement of the framework agreement on behalf of itself for works in the Republic of Ireland (ROI) and on behalf of Northern Ireland Electricity Networks Limited (NIE Networks) for works in Northern Ireland (NI) and is the Contracting Entity for the purposes of this Procurement. The individual Framework Agreement will be a tri-partite agreement between the Contractor, ESB and NIE Networks. The successful Contractors to this Framework Agreement should be willing to undertake works in Northern Ireland on behalf of NIE Networks and in the Republic of Ireland on behalf on ESB. Drawdown of call off contracts under the Framework Agreement will be as either direct award or by mini-competition with eligible contractors.
Post-award of the Framework Agreement, ESB will be the contracting party that is responsible for call-off contracts awarded for works in the Republic of Ireland (ROI) and NIE Networks will be the contracting party responsible for call-off contracts awarded for works in Northern Ireland (NI).
The multi-contractor Framework Agreement will involve the construction of a single circuit 400 kV overhead transmission line supported by circa 401 towers for a distance of circa 140 km from a new NIE Networks substation at Turleenan, Co. Tyrone to the existing ESB substation in Woodland, Co Meath.
Without prejudice to ESB’s rights as set out herein and in the pre-qualification questionnaire, please note that all relevant consents have not yet been received for the entirety of this project and ESB may therefore cancel this procurement process.
Price is not the only award criterion and all criteria are stated only in the procurement documents
II.2.7)
Duration of the contract, framework agreement or dynamic purchasing system
Duration in months:
60
This contract is subject to renewal:
yes
Description of renewals:
Option to extend, at the discretion of ESB and NIE Networks, for up to three (3) further years.
II.2.9)
Information about the limits on the number of candidates to be invited
Envisaged number of candidates:
10
II.2.10)
Information about variants
Variants will be accepted:
no
II.2.11)
Information about options
Options:
no
II.2.13)
Information about European Union funds
The procurement is related to a project and/or programme financed by European Union funds:
no