[QuantityScopeContract]
Multi Party Framework Agreement for the Provision of Energy Efficiency Retrofitting in Dublin City Council Housing Stock in 12 Lots
[Fileref]:
RTF 164039
[Works]
Dublin City Council (DCC) has established a Multi-Party Framework Agreement for the procurement of works contractors for term maintenance and refurbishment work associated with the Energy Efficiency Retrofit to Dublin City Councils housing units in the Dublin City Council Areas marked out as Lots 1 to 12. Tenderers applied for inclusion in one, some, or all lots. Each lot was allocated €2 million for 2 years. Each Lot will involve the allocation of an average of 40 houses per contract. This may increase subject to receiving additional funding for the project.
Within each framework work will be allocated in tranches of 5 to 15 houses (average 10). Please see Volume A Statement of Requirements and Framework Agreement for use with Term Maintenance and Refurbishment Works Contract for further information.
[DivisionLots]:
[Yes]
[ValueExclVat]:
24000000.00
EUR
Lot 1 - Finglas West
[LotNumber]:
1
44221110
-
45261410
-
45320000
-
45410000
-
45421112
-
II.2.3)
[PlacePerformance]
[MainsiteplaceWorksDelivery]:
Dublin City Council Administrative Area
II.2.4)
[DescrProcurement]
Energy Efficiency Retrofitting Upgrade Works to houses located in Finglas West.
[AwardCriteriaBelow]
[AwardCriterionQuality]
-
[AwardCriterionName]:
Criterion B: Speed of Tranche Completion
/
[Weighting]:
15%
[AwardCriterionQuality]
-
[AwardCriterionName]:
Criterion C: Project Management Methodology
/
[Weighting]:
15%
[Price]
-
[Weighting]:
70%
[Options]:
[No]
[EuProgrRelated]:
[Yes]
[EuProgrRef]:
Energy Efficiency works carried out under Phase 2 of the Programme are eligible, at a national level, for 50% co-funding under the European Regional Development Fund (ERDF) 2014 – 2020 operational programmes. The principle objective of the programme is to meet Ireland’s commitments in relation to carbon emissions reduction and energy reduction targets for 2020.
Lot 2 - Finglas East
[LotNumber]:
2
44221110
-
45261410
-
45320000
-
45410000
-
45421112
-
II.2.3)
[PlacePerformance]
[MainsiteplaceWorksDelivery]:
Dublin City Council Administrative Area
II.2.4)
[DescrProcurement]
Energy Efficiency Retrofitting Upgrade Works to houses located in Finglas East.
[AwardCriteriaBelow]
[AwardCriterionQuality]
-
[AwardCriterionName]:
Criterion B: Speed of Tranche Completion
/
[Weighting]:
15%
[AwardCriterionQuality]
-
[AwardCriterionName]:
Criterion C: Project Management Methodology
/
[Weighting]:
15%
[Price]
-
[Weighting]:
70%
[Options]:
[No]
[EuProgrRelated]:
[Yes]
[EuProgrRef]:
Energy Efficiency works carried out under Phase 2 of the Programme are eligible, at a national level, for 50% co-funding under the European Regional Development Fund (ERDF) 2014 – 2020 operational programmes. The principle objective of the programme is to meet Ireland’s commitments in relation to carbon emissions reduction and energy reduction targets for 2020.
Lot 3 - Artane / Whitehall
[LotNumber]:
3
44221110
-
45261410
-
45320000
-
45410000
-
45421112
-
II.2.3)
[PlacePerformance]
[MainsiteplaceWorksDelivery]:
Dublin City Council Administrative Area
II.2.4)
[DescrProcurement]
Energy Efficiency Retrofitting Upgrade Works to houses located in Artane / Whitehall.
[AwardCriteriaBelow]
[AwardCriterionQuality]
-
[AwardCriterionName]:
Criterion B: Speed of Tranche Completion
/
[Weighting]:
15%
[AwardCriterionQuality]
-
[AwardCriterionName]:
Criterion C: Project Management Methodology
/
[Weighting]:
15%
[Price]
-
[Weighting]:
70%
[Options]:
[No]
[EuProgrRelated]:
[Yes]
[EuProgrRef]:
Energy Efficiency works carried out under Phase 2 of the Programme are eligible, at a national level, for 50% co-funding under the European Regional Development Fund (ERDF) 2014 – 2020 operational programmes. The principle objective of the programme is to meet Ireland’s commitments in relation to carbon emissions reduction and energy reduction targets for 2020.
Lot 4 - Donaghmede
[LotNumber]:
4
44221110
-
45261410
-
45320000
-
45410000
-
45421112
-
II.2.3)
[PlacePerformance]
[MainsiteplaceWorksDelivery]:
Dublin City Council Administrative Area
II.2.4)
[DescrProcurement]
Energy Efficiency Retrofitting Upgrade Works to houses located in Donaghmede.
[AwardCriteriaBelow]
[AwardCriterionQuality]
-
[AwardCriterionName]:
Criterion B: Speed of Tranche Completion
/
[Weighting]:
15%
[AwardCriterionQuality]
-
[AwardCriterionName]:
Criterion C: Project Management Methodology
/
[Weighting]:
15%
[Price]
-
[Weighting]:
70%
[Options]:
[No]
[EuProgrRelated]:
[Yes]
[EuProgrRef]:
Energy Efficiency works carried out under Phase 2 of the Programme are eligible, at a national level, for 50% co-funding under the European Regional Development Fund (ERDF) 2014 – 2020 operational programmes. The principle objective of the programme is to meet Ireland’s commitments in relation to carbon emissions reduction and energy reduction targets for 2020.
Lot 5 - Clontarf
[LotNumber]:
5
44221110
-
45261410
-
45320000
-
45410000
-
45421112
-
II.2.3)
[PlacePerformance]
[MainsiteplaceWorksDelivery]:
Dublin City Council Administrative Area
II.2.4)
[DescrProcurement]
Energy Efficiency Retrofitting Upgrade Works to houses located in Clontarf
[AwardCriteriaBelow]
[AwardCriterionQuality]
-
[AwardCriterionName]:
Criterion B: Speed of Tranche Completion
/
[Weighting]:
15%
[AwardCriterionQuality]
-
[AwardCriterionName]:
Criterion C: Project Management Methodology
/
[Weighting]:
15%
[Price]
-
[Weighting]:
70%
[Options]:
[No]
[EuProgrRelated]:
[Yes]
[EuProgrRef]:
Energy Efficiency works carried out under Phase 2 of the Programme are eligible, at a national level, for 50% co-funding under the European Regional Development Fund (ERDF) 2014 – 2020 operational programmes. The principle objective of the programme is to meet Ireland’s commitments in relation to carbon emissions reduction and energy reduction targets for 2020.
Lot 6 - Cabra / Glasnevin
[LotNumber]:
6
44221110
-
45261410
-
45320000
-
45410000
-
45421112
-
II.2.3)
[PlacePerformance]
[MainsiteplaceWorksDelivery]:
Dublin City Council Administrative Area
II.2.4)
[DescrProcurement]
Energy Efficiency Retrofitting Upgrade Works to houses located in Cabra / Glasnevin
[AwardCriteriaBelow]
[AwardCriterionQuality]
-
[AwardCriterionName]:
Criterion B: Speed of Tranche Completion
/
[Weighting]:
15%
[AwardCriterionQuality]
-
[AwardCriterionName]:
Criterion C: Project Management Methodology
/
[Weighting]:
15%
[Price]
-
[Weighting]:
70%
[Options]:
[No]
[EuProgrRelated]:
[Yes]
[EuProgrRef]:
Energy Efficiency works carried out under Phase 2 of the Programme are eligible, at a national level, for 50% co-funding under the European Regional Development Fund (ERDF) 2014 – 2020 operational programmes. The principle objective of the programme is to meet Ireland’s commitments in relation to carbon emissions reduction and energy reduction targets for 2020.
Lot 7 - North Inner City
[LotNumber]:
7
44221110
-
45261410
-
45320000
-
45410000
-
45421112
-
II.2.3)
[PlacePerformance]
[MainsiteplaceWorksDelivery]:
Dublin City Council Administrative Area
II.2.4)
[DescrProcurement]
Energy Efficiency Retrofitting Upgrade Works to houses located in North Inner City
[AwardCriteriaBelow]
[AwardCriterionQuality]
-
[AwardCriterionName]:
Criterion B: Speed of Tranche Completion
/
[Weighting]:
15%
[AwardCriterionQuality]
-
[AwardCriterionName]:
Criterion C: Project Management Methodology
/
[Weighting]:
15%
[Price]
-
[Weighting]:
70%
[Options]:
[No]
[EuProgrRelated]:
[Yes]
[EuProgrRef]:
Energy Efficiency works carried out under Phase 2 of the Programme are eligible, at a national level, for 50% co-funding under the European Regional Development Fund (ERDF) 2014 – 2020 operational programmes. The principle objective of the programme is to meet Ireland’s commitments in relation to carbon emissions reduction and energy reduction targets for 2020.
Lot 8 - South Inner City
[LotNumber]:
8
44221110
-
45261410
-
45320000
-
45410000
-
45421112
-
II.2.3)
[PlacePerformance]
[MainsiteplaceWorksDelivery]:
Dublin City Council Administrative Area
II.2.4)
[DescrProcurement]
Energy Efficiency Retrofitting Upgrade Works to houses located in South Inner City.
[AwardCriteriaBelow]
[AwardCriterionQuality]
-
[AwardCriterionName]:
Criterion B: Speed of Tranche Completion
/
[Weighting]:
15%
[AwardCriterionQuality]
-
[AwardCriterionName]:
Criterion C: Project Management Methodology
/
[Weighting]:
15%
[Price]
-
[Weighting]:
70%
[Options]:
[No]
[EuProgrRelated]:
[Yes]
[EuProgrRef]:
Energy Efficiency works carried out under Phase 2 of the Programme are eligible, at a national level, for 50% co-funding under the European Regional Development Fund (ERDF) 2014 – 2020 operational programmes. The principle objective of the programme is to meet Ireland’s commitments in relation to carbon emissions reduction and energy reduction targets for 2020.
Lot 9 - Ballyfermot West
[LotNumber]:
9
44221110
-
45261410
-
45320000
-
45410000
-
45421112
-
II.2.3)
[PlacePerformance]
[MainsiteplaceWorksDelivery]:
Dublin City Council Administrative Area
II.2.4)
[DescrProcurement]
Energy Efficiency Retrofitting Upgrade Works to houses located in Ballyfermot West
[AwardCriteriaBelow]
[AwardCriterionQuality]
-
[AwardCriterionName]:
Criterion B: Speed of Tranche Completion
/
[Weighting]:
15%
[AwardCriterionQuality]
-
[AwardCriterionName]:
Criterion C: Project Management Methodology
/
[Weighting]:
15%
[Price]
-
[Weighting]:
70%
[Options]:
[No]
[EuProgrRelated]:
[Yes]
[EuProgrRef]:
Energy Efficiency works carried out under Phase 2 of the Programme are eligible, at a national level, for 50% co-funding under the European Regional Development Fund (ERDF) 2014 – 2020 operational programmes. The principle objective of the programme is to meet Ireland’s commitments in relation to carbon emissions reduction and energy reduction targets for 2020.
Lot 10 - Ballyfermot East
[LotNumber]:
10
44221110
-
45261410
-
45320000
-
45410000
-
45421112
-
II.2.3)
[PlacePerformance]
[MainsiteplaceWorksDelivery]:
Dublin City Council Administrative Area
II.2.4)
[DescrProcurement]
Energy Efficiency Retrofitting Upgrade Works to houses located in Ballyfermot East
[AwardCriteriaBelow]
[AwardCriterionQuality]
-
[AwardCriterionName]:
Criterion B: Speed of Tranche Completion
/
[Weighting]:
15%
[AwardCriterionQuality]
-
[AwardCriterionName]:
Criterion C: Project Management Methodology
/
[Weighting]:
15%
[Price]
-
[Weighting]:
70%
[Options]:
[No]
[EuProgrRelated]:
[Yes]
[EuProgrRef]:
Energy Efficiency works carried out under Phase 2 of the Programme are eligible, at a national level, for 50% co-funding under the European Regional Development Fund (ERDF) 2014 – 2020 operational programmes. The principle objective of the programme is to meet Ireland’s commitments in relation to carbon emissions reduction and energy reduction targets for 2020.
Lot 11 - Kimmage / Rathmines / Pembroke
[LotNumber]:
11
44221110
-
45261410
-
45320000
-
45410000
-
45421112
-
II.2.3)
[PlacePerformance]
[MainsiteplaceWorksDelivery]:
Dublin City Council Administrative Area
II.2.4)
[DescrProcurement]
Energy Efficiency Retrofitting Upgrade Works to houses located in Kimmage / Rathmines / Pembroke.
[AwardCriteriaBelow]
[AwardCriterionQuality]
-
[AwardCriterionName]:
Criterion B: Speed of Tranche Completion
/
[Weighting]:
15%
[AwardCriterionQuality]
-
[AwardCriterionName]:
Criterion C: Project Management Methodology
/
[Weighting]:
15%
[Price]
-
[Weighting]:
70%
[Options]:
[No]
[EuProgrRelated]:
[Yes]
[EuProgrRef]:
Energy Efficiency works carried out under Phase 2 of the Programme are eligible, at a national level, for 50% co-funding under the European Regional Development Fund (ERDF) 2014 – 2020 operational programmes. The principle objective of the programme is to meet Ireland’s commitments in relation to carbon emissions reduction and energy reduction targets for 2020.
Lot 12 - Citywide
[LotNumber]:
12
44221110
-
45261410
-
45320000
-
45410000
-
45421112
-
II.2.3)
[PlacePerformance]
[MainsiteplaceWorksDelivery]:
Dublin City Council Administrative Area
II.2.4)
[DescrProcurement]
Special Energy Efficiency Retrofitting Upgrade projects Citywide.
[AwardCriteriaBelow]
[AwardCriterionQuality]
-
[AwardCriterionName]:
Criterion B: Speed of Tranche Completion
/
[Weighting]:
15%
[AwardCriterionQuality]
-
[AwardCriterionName]:
Criterion C: Project Management Methodology
/
[Weighting]:
15%
[Price]
-
[Weighting]:
70%
[Options]:
[No]
[EuProgrRelated]:
[Yes]
[EuProgrRef]:
Energy Efficiency works carried out under Phase 2 of the Programme are eligible, at a national level, for 50% co-funding under the European Regional Development Fund (ERDF) 2014 – 2020 operational programmes. The principle objective of the programme is to meet Ireland’s commitments in relation to carbon emissions reduction and energy reduction targets for 2020.