Contract award notice

Information

Published

Date of dispatch of this notice: 21/11/2019

External Reference: 2019-287084

TED Reference: 2019/S 227-556344

Contract award notice

Contract award notice

Results of the procurement procedure

Directive 2014/24/EU

Section I: Contracting authority

I.1)

Name and addresses

Galway County Council
N/A
County Hall
Galway
Prospect Hill
IE
Contact person: cathal Joyce
Telephone: +353 91509096
Internet address(es):
I.4)

Type of the contracting authority

Regional or local authority
I.5)

Main activity

General public services

Section II: Object

II.1)

Scope of the procurement

II.1.1)

Title

N59 Maam Cross to Bunnakill
Reference number:  N59 Maam Cross to Bunnakill
II.1.2)

Main CPV code

45233121  -  Main road construction works
II.1.3)

Type of contract

Works
II.1.4)

Short description

The proposed development consists of the realignment of a section of the existing N59 between Maam Cross and the townland of Bunnakill in County Galway. This section of road is approximately 5km in length and involves the construction of a new Type 3 standard single carriageway consisting of a 6m carriageway, 0.5m hard strips and verges of approximately 2m to 3m. Upgrades also include the improvement / realignment of a number of local and access roads.The Project includes earthworks in challenging ground conditions, excavation and replacement of substantial quantities of peat, including removal of peat underlying existing road and the construction of two peat restoration areas and five material deposition sites.There are a number of structures on the scheme possibly including two new bridges and two retaining walls.
The proposed scheme is located in an environmentally sensitive area and environmental mitigation measures will form a very important aspect of the scheme.
II.1.6)

Information about lots

This contract is divided into lots: no
II.1.7)

Total value of the procurement

Value excluding VAT:  16561764.60  EUR
II.2)

Description

II.2.2)

Additional CPV code(s)

45000000  -  Construction work
45200000  -  Works for complete or part construction and civil engineering work
45220000  -  Engineering works and construction works
45221100  -  Construction work for bridges
45221110  -  Bridge construction work
45221111  -  Road bridge construction work
45230000  -  Construction work for pipelines, communication and power lines, for highways, roads, airfields and railways; flatwork
45233000  -  Construction, foundation and surface works for highways, roads
45233100  -  Construction work for highways, roads
45233120  -  Road construction works
45233125  -  Road junction construction work
45233127  -  T-junction construction work
II.2.3)

Place of performance

Main site or place of performance:  
Co. Galway
II.2.4)

Description of the procurement

The proposed development consists of the realignment of a section of the existing N59 between Maam Cross and the townland of Bunnakill in County Galway.
This section of road is approximately 5km in length and involves the construction of a new Type 3 standard single carriageway consisting of a 6m carriageway, 0.5m hard strips and verges of approximately 2m to 3m. Upgrades also include the improvement / realignment of a number of local and access roads.
The Project includes earthworks in challenging ground conditions, excavation and replacement of substantial quantities of peat, including removal of peat underlying existing road and the construction of two peat restoration areas and five material deposition sites.
There are a number of structures on the scheme possibly including two new bridges and two retaining walls.
The proposed scheme is located in an environmentally sensitive area and environmental mitigation measures will form a very important aspect of the scheme.
II.2.5)

Award criteria

Criteria below
Price
II.2.11)

Information about options

Options: no
II.2.13)

Information about European Union funds

The procurement is related to a project and/or programme financed by European Union funds: no
II.2.14)

Additional information

The construction of this 5km section of national road
in the connamara region will require careful
construction mitigation to meet the requirements laid
out in the environmental impact statement. The
project includes some bridge works with a
considerable amount of peat excavation.

Section IV: Procedure

IV.1)

Description

IV.1.1)

Type of procedure

Restricted procedure
IV.1.8)

Information about the Government Procurement Agreement (GPA)

The procurement is covered by the Government Procurement Agreement : yes
IV.2)

Administrative information

IV.2.1)

Previous publication concerning this procedure

Notice number in the OJ S: 2018/S 145-330893

Section V: Award of contract

Contract No: 1

Title: N59 Maam Cross to Bunnakill

A contract/lot is awarded: yes
V.2)

Award of contract

V.2.1)

Date of conclusion of the contract

01/11/2019
V.2.2)

Information about tenders

Number of tenders received:  4
Number of tenders received by electronic means:  4
The contract has been awarded to a group of economic operators :  no
V.2.3)

Name and address of the contractor

Clare Civil Engineering
4633874G
608 Jordanstown Road
Co. Dublin
Greenogue Business P
IE
Telephone: +353 012572740
Fax: +353 012572232

The contractor is an SME : yes
V.2.4)

Information on value of the contract/lot (excluding VAT)

Total value of the contract/lot:  16561764.60  EUR

Section VI: Complementary information

VI.4)

Procedures for review

VI.4.1)

Review body

N59 Maam Cross to Bunnakill
Galway
IE