II.1)
Scope of the procurement
N67 Ballinderreen to Kinvara Phase 2 Road Realignment
Reference number:
GCC Road Realignment N67
45233100
-
Construction work for highways, roads
Works
II.1.4)
Short description
The N67 Ballinderreen to Kinvara Road Realignment Scheme consists of the improvement of approximately 3km of the N67 National Secondary Road between Ballinderreen and Kinvara. Galway County Council is advancing this road re-alignment, which includes:
- approx. 3km
- Re-alignment of 7 side road junctions
- Various reconfigured accommodation works accesses.
- The scheme comprises of on-line widening with some sections of off-line construction.
- Combined Cycletrack and Footway
- Various Retaining Walls.
II.1.5)
Estimated total value
Value excluding VAT: 6100000.00
EUR
II.1.6)
Information about lots
This contract is divided into lots:
no
II.2.2)
Additional CPV code(s)
45233110
-
Motorway construction works
45233120
-
Road construction works
45233121
-
Main road construction works
45233123
-
Secondary road construction work
45233124
-
Trunk road construction work
45233125
-
Road junction construction work
45233127
-
T-junction construction work
45233129
-
Crossroad construction work
45233130
-
Construction work for highways
45233139
-
Highway maintenance work
45233140
-
Roadworks
45233141
-
Road-maintenance works
45233142
-
Road-repair works
45233160
-
Paths and other metalled surfaces
45233162
-
Cycle path construction work
II.2.3)
Place of performance
Main site or place of performance:
Kinvara
II.2.4)
Description of the procurement
The N67 Ballinderreen to Kinvara Road
Realignment Scheme consists of the improvement
of approximately 3km of the N67 National
Secondary Road between Ballinderreen and
Kinvara.
Includes: Re-alignment of 7 side road junctions.
Various reconfigured accommodation works
accesses. On-line widening with some sections of off-
line construction. Combined cycletrack and footway.
Various retaining walls.
Criteria below
Cost criterion
-
Name:
Cost
/
Weighting:
100
Value excluding VAT: 6100000.00
EUR
II.2.7)
Duration of the contract, framework agreement or dynamic purchasing system
Duration in months:
18
This contract is subject to renewal:
no
II.2.10)
Information about variants
Variants will be accepted:
no
II.2.11)
Information about options
Options:
no
II.2.13)
Information about European Union funds
The procurement is related to a project and/or programme financed by European Union funds:
no