Corrigendum

Information

Published

Date of dispatch of this notice: 09/03/2023

External Reference: 2023-208210

TED Reference: 2023/S 052-153573

Corrigendum

Corrigendum

Notice for changes or additional information

Works

Directive 2014/24/EU

Section I: Contracting authority/entity

I.1)

Name and addresses

National Development Finance Agency
N/A
Treasury Dock, North Wall Quay
Dublin
D01 A9T8
IE
Contact person: Ciaran Doyle
Telephone: +353 16640800
NUTS code:  IE -  IRELAND
Internet address(es):
Main address: www.NDFA.ie

Section II: Object

II.1)

Scope of the procurement

II.1.1)

Title

Social Housing PPP Programme - Bundle 3
II.1.2)

Main CPV code

45000000  -  Construction work
II.1.3)

Type of contract

Works
II.1.4)

Short description

Following on from the Prior Information Notice (“PIN”), the National Treasury Management Agency (describing itself as the National Development Finance Agency) (the “NDFA”) acting for and on behalf of the Department of Housing, Local Government and Heritage (as Approving Authority) and Dublin City Council (as Sponsoring Agency, Lead Local Authority and Contracting Authority for the Project) intends to procure, by Public Private Partnership (“PPP”), the design, build, finance, operation and maintenance of a number of social housing developments in Ireland, located in the counties of Dublin, Kildare, Wicklow and Sligo. The project is the third project bundle of the Social Housing PPP Programme. It is anticipated that (based on current inflation predictions) the project will have a capital value of €150 million (excluding VAT).

Section VI: Complementary information

VI.6)

Original notice reference

Notice number in the OJ S: 2022/S 246-712997

Section VII: Changes

VII.1)

Information to be changed or added

VII.1.2)

Text to be corrected in the original notice

Section number:  IV 2.2
Instead of:  
Date:  21/03/2023
Local time:  12:00
Read:  
Date:  12/04/2023
Local time:  12:00
VII.2)

Other additional information

Extension of Time
Closing Date and Time
The Closing Date and Time for Prequalification Submissions as defined in
section 5.10 of the Project Information Memorandum (PIM) is extended to
12:00pm Irish time on Wednesday 12 April 2023.
The closing date and time for enquiries is extended to 12:00pm Irish time on
Tuesday 28 March 2023.
The NDFA will endeavour to respond to all enquiries by Tuesday 4 April 2023
however does not undertake to respond to all enquiries received.