Mechanical Specialist (2019) - Archival Repository Project, Bishop Street, Dublin 8
Reference number:
ARP Mechanical Specialist (2019)
45350000
-
Mechanical installations
Works
II.1.4)
Short description
The proposed development at the warehouse of the National Archives of Ireland, Dublin 8, comprising approx. gross floor area of 5,200m2, consists of the construction of ground and new first floor archive repository accommodation and circulation areas, with climate control and fire protection. Construction will take place within the existing warehouse walls and roof. The existing floor slab will be removed and replaced by new foundations and floor slab at finished floor level of the existing ground floor. The structure will be a self-supporting in-situ reinforced concrete framework. Vertical circulation between ground floor and first floor will be provided via four separate stair cores and two separate lifts. Two of the four stair cores will be continued to the attic space to facilitate maintenance access. Lift access to the attic is not proposed.
II.1.6)
Information about lots
This contract is divided into lots:
no
II.2.2)
Additional CPV code(s)
45000000
-
Construction work
45300000
-
Building installation work
45350000
-
Mechanical installations
II.2.3)
Place of performance
NUTS code:
IE061 -
Dublin
Main site or place of performance:
Bishop St., Dublin 8
II.2.4)
Description of the procurement
The National Archives of Ireland holds official State documents and records for preservation. The documents are kept at buildings in Bishop Street, Dublin 8 where there are public reading rooms and storage facilities for the documents. There are two distinct buildings on the site, an office block where the reading rooms, staff offices and some storage are housed and an adjoining warehouse for the storage of the archives. The National Archives will continue to be occupied and operate during the construction period.
The proposed development, comprising approx. gross floor area of 5,200m2, consists of the construction of ground and new first floor archive repository accommodation and circulation areas, with climate control and fire protection. Construction will take place within the existing warehouse walls and roof. The existing floor slab will be removed and replaced by new foundations and floor slab at finished floor level of the existing ground floor. The structure will be a self-supporting in-situ reinforced concrete framework. Vertical circulation between ground floor and first floor will be provided via four separate stair cores and two separate lifts. Two of the four stair cores will be continued to the attic space to facilitate maintenance access. Lift access to the attic is not proposed.
The only external works are the replacement of clerestory windows, the widening of an existing escape door and the addition of one escape door, both onto Bride Street. An existing wall with door onto the car park to the East of the warehouse will be widened to accommodate access during the construction period and reversed to reinstate the existing wall and door.
A mobile racking shelving system will be installed under a separate contract.
II.2.11)
Information about options
Options:
no
II.2.13)
Information about European Union funds
The procurement is related to a project and/or programme financed by European Union funds:
no
II.2.14)
Additional information
*Tenders are to be submitted to Claire McKevett, Major Projects, Office of Public Works, 52 St. Stephen's Green, Dublin 2
* Please provide 1 hard copy and 1 soft copy (On
CD
or USB stick in PDF format) of your submission.
* Please mark envelope: 'Pre-Qual-Mechanical'
*Submissions CANNOT be made via e-tenders.