II.1)
Scope of the procurement
Grange Road to Tramore Valley Pedestrian and Cycle Link
Reference number:
CCC/092/21
45233162
-
Cycle path construction work
Works
II.1.4)
Short description
The scheme is to provide a pedestrian and cycle link between Grange Road and Tramore Valley Park and includes:
The 5m wide pedestrian/cycle track is to be constructed on a constrained site through the existing woodland requiring site clearance and tree felling.
The pavement will be constructed on earthworks/vegetated and mechanically stabilised embankments along its length.
The N40 pedestrian/cycle overbridge comprises a 2-span steel structure. The main northern bridge span over the dual carriageway comprises a 46.57m truss and 16m southern span comprises steel beams over the Cork City and Harbour Watermain.
Landscaping, permanent fencing, pavement markings and bespoke signage are required along the track.