Scope of the procurement
Pressing of Front-End Panels for ICR Fleet
Reference number:
7458A
34210000
-
Vehicle bodies
Supplies
II.1.4)
Short description
Iarnród Éireann (IÉ) is seeking to enter into a supply agreement with a specialist company[s] with a demonstrable track record in the pressing of aluminium components or similar products to facilitate the Pressing of Front-End Panels for its Inter City Railcar [ICR] Fleet.
IÉ wish to start a replacement programme which will be carried out coinciding with the degraded condition of the front-end panels on the trains. As the panels are overdue a replacement on a significant number of ICR lead cars, this will require the removal of the degraded front-end panel from the vehicles and replacing them with new panels.
There is a total of of 63 train sets, 126 lead cars with both a left and right front-end panel and 24 spares. Total of 150 pairs.
II.1.6)
Information about lots
This contract is divided into lots:
no
II.2.2)
Additional CPV code(s)
34600000
-
Railway and tramway locomotives and rolling stock and associated parts
34610000
-
Rail locomotives and tenders
34621000
-
Railway maintenance or service vehicles, and railway freight wagons
II.2.3)
Place of performance
Main site or place of performance:
Inchicore, Dublin 8
II.2.4)
Description of the procurement
Iarnród Éireann (IÉ) is seeking to enter into a supply agreement with a specialist company[s] with a demonstrable track record in the pressing of aluminium components or similar products to facilitate the Pressing of Front-End Panels for its Inter City Railcar [ICR] Fleet.
IÉ wish to start a replacement programme which will be carried out coinciding with the degraded condition of the front-end panels on the trains. As the panels are overdue a replacement on a significant number of ICR lead cars, this will require the removal of the degraded front-end panel from the vehicles and replacing them with new panels.
The front-end panels are designed for the aesthetic presentation of the train and to protect underbody equipment from large debris on the track. The panels typically receive on track collisions with ballast animals, rubbish etc. The ICR’s operate at all speeds up to 161kph.
Quantity Required: There is a total of of 63 train sets, 126 lead cars with both a left and right front-end panel and 24 spares. Total of 150 pairs.
IÉ Core Requirement:
The basic requirements for the pressing of the panels as required by IÉ will cover [but may not be limited to] the following:
• IÉ require in excess of 150 pairs of front-end panels [left and right].
• The preference of IÉ is for the contactor to deliver all 150 pairs of front-end panels in one delivery.
• The contractor is to provide details on their proposed delivery schedule.
• The front-end panels are to be pressed from Aluminium Alloy 5754.
• The front-end panels are to be pressed from aluminium using two larges dies supplied by IÉ.
II.2.11)
Information about options
Options:
no
II.2.13)
Information about European Union funds
The procurement is related to a project and/or programme financed by European Union funds:
no