II.1)
Scope of the procurement
IDA Waterford Infrastructure Upgrade Works
Reference number:
IDA Waterford B&T Park
45000000
-
Construction work
Works
II.1.4)
Short description
The existing road surface which is a mix of Concrete/ Asphalt/ Concrete with Asphalt overlay is to be removed and replaced with a new Asphalt surface over bitumen base and road base course with regulation of the sub grade.
Removal of existing and replacement of all footpath and kerbing as noted on the drawings.
Provision of new cycle lane to parts of the Business Park.
Removal in part and upgrade of foul and surface water infrastructure.
Removal and replacement of existing asbestos watermain with new watermain throughout the park complete with all fixtures and fittings, values and chambers.
Localised replace and replacement of utility and service chamber frames and covers, ducting and public lighting.
Associated accommodation works and retaining structures to facilitate the new construction elements.
The full scope of the Works and the obligations of the Contractor are to be ascertained by reference to the Contract Documents and Drawings as a whole.
II.1.5)
Estimated total value
Value excluding VAT: 5500000.00
EUR
II.1.6)
Information about lots
This contract is divided into lots:
no
II.2.2)
Additional CPV code(s)
45200000
-
Works for complete or part construction and civil engineering work
45233100
-
Construction work for highways, roads
45233120
-
Road construction works
45233121
-
Main road construction works
45233141
-
Road-maintenance works
45233142
-
Road-repair works
45233220
-
Surface work for roads
II.2.3)
Place of performance
Main site or place of performance:
IDA Raheen B&T Park, Limerick, Ireland
II.2.4)
Description of the procurement
There are main objectives as part of the Waterford Infrastructure Upgrade Works:
The existing road surface which is a mix of Concrete/ Asphalt/ Concrete with Asphalt overlay is to be removed and replaced with a new Asphalt surface over bitumen base and road base course with regulation of the sub grade.
Removal of existing and replacement of all footpath and kerbing as noted on the drawings.
Provision of new cycle lane to parts of the Business Park.
Removal in part and upgrade of foul and surface water infrastructure.
Removal and replacement of existing asbestos watermain with new watermain throughout the park complete with all fixtures and fittings, values and chambers.
Localised replace and replacement of utility and service chamber frames and covers, ducting and public lighting.
Associated accommodation works and retaining structures to facilitate the new construction elements.
The full scope of the Works and the obligations of the Contractor are to be ascertained by reference to the Contract Documents and Drawings as a whole.
Price is not the only award criterion and all criteria are stated only in the procurement documents
Value excluding VAT: 5500000.00
EUR
II.2.7)
Duration of the contract, framework agreement or dynamic purchasing system
Duration in months:
18
This contract is subject to renewal:
no
II.2.10)
Information about variants
Variants will be accepted:
no
II.2.11)
Information about options
Options:
no
II.2.13)
Information about European Union funds
The procurement is related to a project and/or programme financed by European Union funds: