In 2011, Bord Na Móna plc published a ‘Strategic Framework for the Future Use of Peatlands’, which reviews and assesses the land bank resource, identifies key issues and considers options for future land-use. This strategy recognises that cutaway peatlands have significant potential for the development of wind energy.
Bord na Móna Plc and specifically Bord na Móna Powergen Ltd. have completed a high-level site selection study examining the potential for developing cutaway peat land for the purposes of Wind Energy production. Arising from the site selection process a number of areas have been selected for further investigation and will require ongoing baseline surveys for breeding and winter birds. These surveys will subsequently act as baseline data for any future Environmental Impact Assessment Report (EIAR) for potential development of the bogs identified.
II.1.6)
Information about lots
This contract is divided into lots:
no
II.2.2)
Additional CPV code(s)
90711000
-
Environmental impact assessment other than for construction
90711400
-
Environmental Impact Assessment (EIA) services other than for construction
90711500
-
Environmental monitoring other than for construction
90712000
-
Environmental planning
II.2.4)
Description of the procurement
Bord Na Móna plc is a commercial semi-state company 95% owned by the state, originally established in 1946 to develop and manage some of Ireland’s extensive peat resources, in accordance with government policy at the time. Bord Na Móna plc lands extend to approximately 80,000 hectares in total and are located mainly in the Irish midlands. In 2011, Bord Na Móna plc published a ‘Strategic Framework for the Future Use of Peatlands’, which reviews and assesses the land bank resource, identifies key issues and considers options for future land-use. This strategy recognises that cutaway peatlands have significant potential for the development of wind energy.
Bord na Móna Plc and specifically Bord na Móna Powergen Ltd. have completed a high-level site selection study examining the potential for developing cutaway peat land for the purposes of Wind Energy production. Arising from the site selection process a number of areas have been selected for further investigation and will require ongoing baseline surveys for breeding and winter birds. These surveys will subsequently act as baseline data for any future Environmental Impact Assessment Report (EIAR) for potential development of the bogs identified.
Price is not the only award criterion and all criteria are stated only in the procurement documents
II.2.7)
Duration of the contract, framework agreement or dynamic purchasing system
Duration in months:
48
This contract is subject to renewal:
no
II.2.10)
Information about variants
Variants will be accepted:
no
II.2.11)
Information about options
Options:
no
II.2.13)
Information about European Union funds
The procurement is related to a project and/or programme financed by European Union funds: