Contract award notice - utilities

Information

Published

Date of dispatch of this notice: 04/06/2020

External Reference: 2020-269811

TED Reference: 2020/S 109-265465

Contract award notice - utilities

Cached Version

Contract award notice – utilities

Results of the procurement procedure

Works

Directive 2014/25/EU

Section I: Contracting entity

I.1)

Name and addresses

Ervia
N/A
P.O.Box 900, Webworks, Eglinton Street
Cork
Cork
IE
Contact person: Tender Admin
Telephone: +353 214239065
NUTS code:  IE -  IRELAND
Internet address(es):
Main address: http://www.ervia.ie

I.6)

Main activity

Water

Section II: Object

II.1)

Scope of the procurement

II.1.1)

Title

Inistioge Water Supply Scheme
Reference number:  15/070
II.1.2)

Main CPV code

45221250  -  Underground work other than tunnels, shafts and subways
II.1.3)

Type of contract

Works
II.1.4)

Short description

The proposed works will include the upgrade of the supply to Grennan WTP with
the installation of a new borehole to supplement the existing boreholes, an
upgrade to Grennan WTP, installation of 17.62 Km of watermain from Grennan to
the existing reservoir at Ballygub, Inistioge, installation of a new reservoir at
Kilmacshane, Inistioge, installation of a booster pumping station at Kilcross,
Inistioge and decommissioning of the existing intake and treatment plant at
Ballygub WTP, together with associated ancillary works.
II.1.6)

Information about lots

This contract is divided into lots: no
II.2)

Description

II.2.2)

Additional CPV code(s)

45231100  -  General construction work for pipelines
45231300  -  Construction work for water and sewage pipelines
45232000  -  Ancillary works for pipelines and cables
45232100  -  Ancillary works for water pipelines
45232151  -  Water-main refurbishment construction work
45232152  -  Pumping station construction work
45240000  -  Construction work for water projects
45247270  -  Reservoir construction works
45317100  -  Electrical installation work of pumping equipment
II.2.3)

Place of performance

NUTS code:  IE -  IRELAND
Main site or place of performance:  
South-East Region
II.2.4)

Description of the procurement

Proposed works will include the upgrade of the
supply to Grennan WTP with the installation of a new
borehole to supplement the existing boreholes, an
upgrade to Grennan WTP, installation of 17.62 Km of
watermain from Grennan to the existing reservoir at
Ballygub, Inistioge, installation of a new reservoir at
Kilmacshane, Inistioge, installation of a booster
pumping station at Kilcross, Inistioge and
decommissioning of the existing intake and
treatment plant at Ballygub WTP
II.2.11)

Information about options

Options: no
II.2.13)

Information about European Union funds

The procurement is related to a project and/or programme financed by European Union funds: no
II.2.14)

Additional information

A pre-qualification questionnaire will be issued to all
candidates who forward an Expression of interest
and send via email for the attention of The Shared
Services Procurement Manager to Tenders@ervia.ie
The questionnaire must be completed and returned
to the address in I.1. above not later than 17.00hrs
Monday 26th October 2015.

Section IV: Procedure

IV.1)

Description

IV.1.1)

Type of procedure

Negotiated procedure with prior call for competition
IV.1.8)

Information about the Government Procurement Agreement (GPA)

The procurement is covered by the Government Procurement Agreement : yes
IV.2)

Administrative information

IV.2.1)

Previous publication concerning this procedure

Notice number in the OJ S: 2015/S 186-337492

Section V: Award of contract

Contract No: 1

Title: 15/070 - Inistioge Water Supply Scheme

A contract/lot is awarded: yes
V.2)

Award of contract

V.2.1)

Date of conclusion of the contract

21/06/2017
V.2.2)

Information about tenders ( Agree to publish? yes )

Number of tenders received:  3
The contract has been awarded to a group of economic operators :  no
V.2.3)

Name and address of the contractor ( Agree to publish? yes )

Ward & Burke Construction Ltd.
Galway
IE
NUTS code:  IE -  IRELAND

The contractor is an SME : no

Section VI: Complementary information

VI.4)

Procedures for review

VI.4.1)

Review body

The High Court
The Four Courts
Dublin
7
IE
Telephone: +353 18886000
Internet address: http://www.courts.ie

VI.4.3)

Review procedure

Precise information on deadline(s) for review procedures: 
Precise information on deadline(s) for review procedures:
Please refer to Statutory Instrument 131 of 2010, European Communities (Award of Contracts by Utility Undertaking) (Review Procedures) Regulations 2010 (and in particular Regulation 7 and 10(2)).