Works Contractor for Design and Build of NUI Galway Student Accommodation Phase 2 (with Novated Design Team)
Reference number:
NUIG/BUILD/036/2018
45000000
-
Construction work
Works
II.1.4)
Short description
This Project represents Phase 2 of a substantial initiative by NUI Galway to develop a commercially viable, modern, appealing and environmentally friendly 471 bed student accommodation on campus. The accommodation will be delivered on a phased basis with the first phase required for immediate fitout on 1st December 2020 to allow for adequate setup in advance of the start of the second semester in January 2021. The second phase will be required for immediate fitout on the 1st April to allow for adequate setup in advance of the summer letting season in May 2021.
A Single Point Design Team including PSDP has been appointed by NUI Galway (refer to prequalification information memorandum) and will be novated to the Works Contractor at Contract Award Stage.
The Works Contractor will be fully responsible for the completion of the novated design and the construction of the project. The form of contract for the project will be the Public
II.1.6)
Information about lots
This contract is divided into lots:
no
II.2.2)
Additional CPV code(s)
45100000
-
Site preparation work
45112700
-
Landscaping work
45210000
-
Building construction work
45212400
-
Accommodation and restaurant buildings
45212411
-
Hotel construction work
45214400
-
Construction work for university buildings
45310000
-
Electrical installation work
45313100
-
Lift installation work
45350000
-
Mechanical installations
45443000
-
Facade work
II.2.3)
Place of performance
Main site or place of performance:
Galway
II.2.4)
Description of the procurement
This Project represents Phase 2 of a substantial initiative by NUI Galway to develop a commercially viable, modern, appealing and environmentally friendly 471 bed student accommodation on campus. The accommodation will be delivered on a phased basis with the first phase required for immediate fitout on 1st December 2020 to allow for adequate setup in advance of the start of the second semester in January 2021. The second phase will be required for immediate fitout on the 1st April to allow for adequate setup in advane of the summer letting season in May 2021.
The proposed development will be located (subject to successful receipt of planning) on a green field site north of the existing Corrib village student accommodation (between the Bioscience Research Building and the Park and Ride facility).
The development will consist of the design and construction of 471 no. bedspaces, generally arranged in cluster of 4-6 5 en-suite bedrooms, with communal living area in each unit. Further communal areas & facilities, internal plant/service rooms, refuse storage and covered cycle storage facilities are also provided to serve the entire development.
A Single Point Design Team including PSDP has been appointed by NUI Galway (refer to prequalification information memorandum) and will be novated to the Works Contractor at Contract Award Stage.
The Works Contractor will be fully responsible for the completion of the novated design and the construction of the project. The form of contract for the project will be the Public
II.2.11)
Information about options
Options:
no
II.2.13)
Information about European Union funds
The procurement is related to a project and/or programme financed by European Union funds: