II.1)
Scope of the procurement
Marina Park Phase 1
Reference number:
CCC/051/19
45000000
-
Construction work
Works
II.1.4)
Short description
The Marina Park Phase 1 project is the construction of a new city centre parkland. The works will include hard and soft landscaped items, site clearance, adjustment of existing site levels (to form new water storage basins), surface water runoff drainage, diversion of an existing watercourse (complete with associated wiers), new pathways (both trafficked and non-trafficked), sand blasted concrete, resin bonded paving, natural stone paving, brushed concrete and a timber gantry walkway. It will also include provision and installation of park furniture, site lighting, rising main, water feature and all associated mechanical and electrical services. A new 250 space car park with associated road and shared cycling / pedestrian path is to be provided along the existing marina.The park will have an open framed steel structure.
II.1.5)
Estimated total value
Value excluding VAT: 5000000.00
EUR
II.1.6)
Information about lots
This contract is divided into lots:
no
II.2.2)
Additional CPV code(s)
44114000
-
Concrete
45112000
-
Excavating and earthmoving work
45112700
-
Landscaping work
45222110
-
Waste disposal site construction work
45223210
-
Structural steelworks
II.2.4)
Description of the procurement
The Marina Park Phase 1 project is the construction of a new city centre parkland.
The works will include hard and soft landscaped items, site clearance, adjustment of existing site levels (to form new water storage basins), surface water runoff drainage, diversion of an existing watercourse (complete with associated wiers), new pathways (both trafficked and non-trafficked), sand blasted concrete, resin bonded paving, natural stone paving, brushed concrete and a timber gantry walkway. It will also include provision and installation of park furniture, site lighting, rising main, water feature and all associated mechanical and electrical services.
A new 250 space car park with associated road and shared cycling / pedestrian path is to be provided along the existing marina, adjoining the Shandon Boat Club. The car parking bays are to consist of grasscrete. There will be some relocation and / or undergrounding of Electrical Lamp Standards and poles. The park will have an open framed steel structure, partially roofed and wall cladded that will house individual pod like structures including toilet facilities and a coffee shop (neither part of the contract but will be provided for with services).
The project will also comprise of 2 number bridge structures spanning over the diverted watercourse, approximately 10m wide, one of which is to be trafficked.
There will be grand scale earthworks in creating the storage basins and the removal and safe disposal of contaminated soil to licensed waste facilities.
There will be liaison with the public, affected businesses, public bodies, charitable organisations and the GAA Cork County Board and member associations for all upcoming events to be held in Pairc Ui Chaoimh.
The contractor will design & construct temporary works, accommodation works and various other Works including diversions of Authorities Utilities, Service Providers and Private Utility Services; Traffic Management for the entire scheme including all the required diversion and traffic warnin
Price is not the only award criterion and all criteria are stated only in the procurement documents
Value excluding VAT: 5000000.00
EUR
II.2.7)
Duration of the contract, framework agreement or dynamic purchasing system
Duration in months:
14
This contract is subject to renewal:
no
II.2.10)
Information about variants
Variants will be accepted:
no
II.2.11)
Information about options
Options:
no
II.2.13)
Information about European Union funds
The procurement is related to a project and/or programme financed by European Union funds:
yes
Identification of the project:
European Regional Funding Development