Periodic indicative Notice - Utilities

Information

Published

Date of dispatch of this notice: 02/08/2018

Expire date: 24/08/2018

External Reference: 2018-996085

TED Reference: 2018/S 149-342854

Periodic indicative Notice - Utilities

Periodic indicative notice – utilities

This notice is a periodic indicative notice only

Works

Directive 2014/25/EU

Section I: Contracting entity

I.1)

Name and addresses

Irish Water
IE3191327JH
The Shared Services Procurement Manager, Ervia
Cork
Co.Cork
IE
Contact person: Tender Admin
Telephone: +353 214239506
NUTS code:  IE -  IRELAND
Internet address(es):
Main address: http://www.ervia.ie

I.3)

Communication

Additional information can be obtained from
the abovementioned address:  
I.6)

Main activity

Water

Section II: Object

II.1)

Scope of the procurement

II.1.1)

Title

Greater Dublin Drainage Project – Terrestrial Pipelines DB Contract & Greater Dublin Drainage Project – Marine Outfall DB Contract
Reference number:  18/087 & 18/088
II.1.2)

Main CPV code

45231300  -  Construction work for water and sewage pipelines
II.1.3)

Type of contract

Works
II.1.4)

Short description

The proposed Greater Dublin Drainage Project will provide;
• A new regional wastewater treatment plant (WwTP) located at Clonshagh in Fingal, County Dublin, Ireland. (Separate PIN Notice Ref 18/086)
• 26km Orbital Sewers including two pumping stations and outfall pipeline, linking the proposed Regional WwTP to the existing regional sewer network and marine outfall (This PIN).
• Marine Outfall discharging 4.5km out to sea from Baldoyle Bay, 1km northeast of Ireland’s Eye (This PIN).
The Works are necessary to facilitate future development in North and West County Dublin and alleviate the treatment pressures that currently exist at Ringsend WwTP. The project will ensure compliance with EU Directives and Irish National Standards.
The attached Preliminary Market Consultation information and project background document provides further details.
II.1.6)

Information about lots

This contract is divided into lots: no
II.2)

Description

II.2.2)

Additional CPV code(s)

44161410  -  Subsea pipelines
45000000  -  Construction work
45221247  -  Tunnelling works
45232424  -  Sewage outfall construction work
45232440  -  Construction work for sewage pipes
45244000  -  Marine construction works
45244100  -  Marine installations
71320000  -  Engineering design services
71322000  -  Engineering design services for the construction of civil engineering works
71322200  -  Pipeline-design services
71332000  -  Geotechnical engineering services
II.2.3)

Place of performance

NUTS code:  IE -  IRELAND
II.2.4)

Description of the procurement

The envisaged scope of works for the proposed Terrestrial Pipelines (18/087) and Marine Outfall (18/088) works includes for the design, build and commissioning of the following:-
• Orbital Sewer from Blanchardstown to the NW of Dublin to the WwTP at Clonshagh (approximately 13.8km)
- Approx. 1km of gravity pipeline through Connolly hospital using trenchless techniques (circa 1,800mm dia., circa 10m depth);
- Approximately 5.4km length of circa 1,400mm dia. rising main;
- Approximately 7.4km length of circa 1,800mm dia. gravity pipeline
• Connection of Orbital Sewer at Blanchardstown;
• Interface and connection with wastewater treatment plant and Abbotstown pumping station for orbital sewer and outfall connection points;
• Interception of existing sewers along Orbital Sewer pipeline route;
• Interception of the existing live North Fringe Sewer & approximately 600m of circa 1,800mm dia. gravity pipeline to the WwTP using trenchless techniques;
• Approximately 5.4km length of circa 1,800mm dia. outfall pipeline from WwTP at Clonshagh to Baldoyle Bay;
• Trenchless crossings of Dublin-Belfast railway, M1 motorway and other roads and rivers along pipeline route.
This preliminary market consultation supersedes the previous market consultation held in September 2015 and PIN Notice Titled ‘Marine construction works’ Ref Number 2015/S 143-264846 advertised 28/07/2015.
The information provided herein is preliminary only and will be superseded by the Pre-Qualification Questionnaire (PQQ). Such information is offered in good faith for the guidance of Applicants, but no warranty or representation is given as to the accuracy or completeness of any of it, and the Contracting Entity and its advisers shall not be under any liability for any error, misstatement or omission. None of the information shall constitute a contract or part of a contract. The Contracting Entity does not make any guarantee in regard to any contract award and/or the volume or value of works to be procured and reserves the right not to follow up this PIN in any way, and no expense incurred by any person in responding to this PIN will be reimbursed.
II.2.14)

Additional information

Irish Water wishes to invite expressions of interest for 18/087 & 18/088. Please complete and return the formatted response as detailed in the attached Preliminary Market Consultation information and project background document & email to tenders@ervia.ie with the tender reference and the tender title in the subject line of the email not later than 12:00hrs (local time) Wednesday 22nd August 2018.
II.3)

Estimated date of publication of contract notice:

30/09/2018

Section IV: Procedure

IV.1)

Description

IV.1.8)

Information about the Government Procurement Agreement (GPA)

The procurement is covered by the Government Procurement Agreement : yes
IV.2)

Administrative information

Section VI: Complementary information

VI.3)

Additional information

Irish Water wishes to invite expressions of interest for 18/087 - Greater Dublin Drainage Project – Terrestrial Pipelines DB Contract & 18/088 - Greater Dublin Drainage Project – Marine Outfall DB Contract. Please complete and return the formatted response as detailed in the attached Preliminary Market Consultation information and project background document and email to tenders@ervia.ie with the tender reference and the tender title in the subject line of the email not later than 12:00hrs (local time) Wednesday 22nd August 2018.