II.1)
Scope of the procurement
Haulbowline Island East Tip Remediation Project, Cork Harbour, Ireland
45220000
-
Engineering works and construction works
Works
II.1.4)
Short description
The Haulbowline East-Tip is located in Cork Harbour Ireland and is
approximately 9ha in size. On the North, South and East it is bordered by the
Cork Harbour Waters and on the West it is bordered by lands under the control
of the Irish Naval Services. The Haulbowline Island East Tip Remediation Project
is to be executed under a Design-Build Contract. The project is to be executed
under regulatory consents.
Details on the Haulbowline Island Project are also available at
www.corkcoco.ie/haulbowline
II.1.6)
Information about lots
This contract is divided into lots:
no
II.1.7)
Total value of the procurement
Value excluding VAT:
7044161.28
EUR
II.2.2)
Additional CPV code(s)
45220000
-
Engineering works and construction works
45243000
-
Coastal-defence works
45244000
-
Marine construction works
90722000
-
Environmental rehabilitation
90722100
-
Industrial site rehabilitation
II.2.3)
Place of performance
NUTS code:
IE053 -
South-West
Main site or place of performance:
Haulbowline Island, Cork Harbour, Ireland
II.2.4)
Description of the procurement
The Works Contract will be for the remediation of the East Tip site at Haulbowline Island, Cork Harbour, Ireland. The objective of these works is to remediate the East Tip in an environmentally and financially sustainable manner in compliance with the planning and waste licence conditions while facilitating value engineering through the promotion and implementation of innovative solutions throughout the procurement, design and construction stages.
The project will include the design and installation of a Perimeter Engineered
Structure (PES) with a maximum permeability 10-5m/s around the perimeter of
the East Tip. The construction is principally in the foreshore area.
Specifically the project will involve the excavation and regrading of the existing
East-Tip landform; the processing of excavated steel slag to achieve an
engineered grade material; the recovery of scrap metal as an inherent part of the
works; and the filling of excavated and processed material in order to create the
formation layer onto which a future capping system will be installed.
Details on the Haulbowline Island Project are also available at www.corkcoco.ie/haulbowline
Criteria below
Quality criterion
-
Name:
Health, Safety and Environment
/
Weighting:
15
Quality criterion
-
Name:
Design
/
Weighting:
15
Quality criterion
-
Name:
Construction Methodology
/
Weighting:
12
Quality criterion
-
Name:
Programme/Phasing of Works
/
Weighting:
9
Quality criterion
-
Name:
Project Team
/
Weighting:
6
Quality criterion
-
Name:
Methods for Managing the Employer's Risk
/
Weighting:
3
Cost criterion
-
Name:
Lowest comparative cost of tender meeting the suitability criteria and satisfying the Works Information
/
Weighting:
40
II.2.11)
Information about options
Options:
no
II.2.13)
Information about European Union funds
The procurement is related to a project and/or programme financed by European Union funds:
no