Short description
Provision of Employers Representatives Services as required for EirGrid Group.
EirGrid Interconnector Ltd (“EIL”) is the owner and operator of the 500MW HVDC
East West Interconnector (“EWIC”).
EWIC connects the Irish and UK transmission systems with the UK Point of
Connection located at Deeside 400kV Substation. The associated connection
agreement between EIL and National Grid includes for the Point of Connection to
be transferred to a new station Connah’s Quay in 2017.
The connection agreement places the responsibility on EIL to design, build and
commission all interface works associated with the new connection, including the
installation of a new section of HVDC cable and any necessary control and
protection equipment. During the associated outage (approx. 30-40 days) to
undertake the above works, EIL will use the opportunity to progress some or all of
the proposed IT & SCM system at the converter stations in Shotton and Portan.
II.1.6)
Information about lots
This contract is divided into lots:
no
II.1.7)
Total value of the procurement
( Agree to publish? yes )
Value excluding VAT:
800000.00
EUR
II.2.2)
Additional CPV code(s)
71310000
-
Consultative engineering and construction services
71311000
-
Civil engineering consultancy services
71316000
-
Telecommunication consultancy services
II.2.3)
Place of performance
NUTS code:
UK -
UNITED KINGDOM
Main site or place of performance:
Wales
II.2.4)
Description of the procurement
Provision of Employers Representatives Services as required for EirGrid Group.
EirGrid Interconnector Ltd (“EIL”) is the owner and operator of the 500MW HVDC
East West Interconnector (“EWIC”).
EWIC connects the Irish and UK transmission systems with the UK Point of
Connection located at Deeside 400kV Substation. The associated connection
agreement between EIL and National Grid includes for the Point of Connection to
be transferred to a new station Connah’s Quay in 2017.
The connection agreement places the responsibility on EIL to design, build and
commission all interface works associated with the new connection, including the
installation of a new section of HVDC cable and any necessary control and
protection equipment. During the associated outage (approx. 30-40 days) to
undertake the above works, EIL will use the opportunity to progress some or all of
the proposed IT & SCM system at the converter stations in Shotton and Portan.
II.2.5)
Award criteria
( Agree to publish? yes )
Criteria below
Quality criterion
-
Name:
Resources
/
Weighting:
30%
Quality criterion
-
Name:
Approach & Methodology
/
Weighting:
20%
Quality criterion
-
Name:
Assessment of Resource Allocation Schedule
/
Weighting:
5%
Quality criterion
-
Name:
Legal
/
Weighting:
5%
Price
-
Weighting:
40%
II.2.11)
Information about options
Options:
no
II.2.13)
Information about European Union funds
The procurement is related to a project and/or programme financed by European Union funds:
no