GWM-2534 - Framework for ESB Wind Farm Long Term Services & Availability Agreements (WTGSAA2016)
Island of Ireland and Wales
GWM-2534 - Framework for ESB Wind Farm Long Term Services & Availability
Agreements (WTGSAA2016)
The existing service agreements for the wind farms which are the subject of this procurement competition expire during 2016/2017.
Three options will be considered:
Option 1: Full Service & Availability Agreement including capital components.
Option 2: Service & Availability Agreement excluding capital components.
Option 3: Supply of capital components and spare parts.
The scope of service will include provision of all materials, plant, equipment, labour and services for the Wind Farm as outlined above for an initial period of 5 years from the Award of Contract, with an option to extend for a further 5 years, or up to the end of design life, which ever is the longer, at the sole discretion of the Contracting Entity .
Applicants should confirm that they will be willing to provide as a minimum Option 1 scope or Option 2 scope as part of their pre-qualification submission. The decision on the final option will be determined either after the pre-qualification assessment or after tender evaluation/negotiation, at the Contracting Entity’s sole discretion.
This wind farm was installed in 2005.
It has 70 no. Vestas V52 0.85MW wind turbines.
Three options will be considered:
Option 1: Full Service & Availability Agreement including capital components.
Option 2: Service & Availability Agreement excluding capital components.
Option 3: Supply of capital components and spare parts.
The scope of service will include provision of all materials, plant, equipment, labour and services for the Wind Farm as outlined above for an initial period of 5 years from the Award of Contract, with an option to extend for a further 5 years, or up to the end of design life, which ever is the longer, at the sole discretion of the Contracting Entity .
The decision on the final option will be determined either after the pre-qualification assessment or after tender evaluation/negotiation, at the Contracting Entity’s sole discretion.
This wind farm was installed in 2002.
It has 14 no. Vestas V52 0.85MW wind turbines.
Three options will be considered:
Option 1: Full Service & Availability Agreement including capital components.
Option 2: Service & Availability Agreement excluding capital components.
Option 3: Supply of capital components and spare parts.
The scope of service will include provision of all materials, plant, equipment, labour and services for the Wind Farm as outlined above for an initial period of 5 years from the Award of Contract, with an option to extend for a further 5 years, or up to the end of design life, which ever is the longer, at the sole discretion of the Contracting Entity .
The decision on the final option will be determined either after the pre-qualification assessment or after tender evaluation/negotiation, at the Contracting Entity’s sole discretion.
This wind farm was installed in 2 phases, 2001 and 2005.
It has 12 no. Vestas V52 0.85MW wind turbines in total.
Three options will be considered:
Option 1: Full Service & Availability Agreement including capital components.
Option 2: Service & Availability Agreement excluding capital components.
Option 3: Supply of capital components and spare parts.
The scope of service will include provision of all materials, plant, equipment, labour and services for the Wind Farm as outlined above for an initial period of 5 years from the Award of Contract, with an option to extend for a further 5 years, or up to the end of design life, which ever is the longer, at the sole discretion of the Contracting Entity .
The decision on the final option will be determined either after the pre-qualification assessment or after tender evaluation/negotiation, at the Contracting Entity’s sole discretion.
This wind farm was installed in 2005.
It has 8 no. Vestas V52 0.85MW wind turbines.
Three options will be considered:
Option 1: Full Service & Availability Agreement including capital components.
Option 2: Service & Availability Agreement excluding capital components.
Option 3: Supply of capital components and spare parts.
The scope of service will include provision of all materials, plant, equipment, labour and services for the Wind Farm as outlined above for an initial period of 5 years from the Award of Contract, with an option to extend for a further 5 years, or up to the end of design life, which ever is the longer, at the sole discretion of the Contracting Entity .
The decision on the final option will be determined either after the pre-qualification assessment or after tender evaluation/negotiation, at the Contracting Entity’s sole discretion.
This wind farm was installed in 2008.
It has 21 no. GE 1.5SE 1.5MW wind turbines.
Three options will be considered:
Option 1: Full Service & Availability Agreement including capital components.
Option 2: Service & Availability Agreement excluding capital components.
Option 3: Supply of capital components and spare parts.
The scope of service will include provision of all materials, plant, equipment, labour and services for the Wind Farm as outlined above for an initial period of 5 years from the Award of Contract, with an option to extend for a further 5 years, or up to the end of design life, which ever is the longer, at the sole discretion of the Contracting Entity .
The decision on the final option will be determined either after the pre-qualification assessment or after tender evaluation/negotiation, at the Contracting Entity’s sole discretion.
This wind farm was installed in 2006.
It has 4 no. Gamesa G52 0.85MW wind turbines.
Three options will be considered:
Option 1: Full Service & Availability Agreement including capital components.
Option 2: Service & Availability Agreement excluding capital components.
Option 3: Supply of capital components and spare parts.
The scope of service will include provision of all materials, plant, equipment, labour and services for the Wind Farm as outlined above for an initial period of 5 years from the Award of Contract, with an option to extend for a further 5 years, or up to the end of design life, which ever is the longer, at the sole discretion of the Contracting Entity .
The decision on the final option will be determined either after the pre-qualification assessment or after tender evaluation/negotiation, at the Contracting Entity’s sole discretion.
This wind farm was installed in 2013.
It has 15 no. Siemens SWT93 2.3MW wind turbines.
Three options will be considered:
Option 1: Full Service & Availability Agreement including capital components.
Option 2: Service & Availability Agreement excluding capital components.
Option 3: Supply of capital components and spare parts.
The scope of service will include provision of all materials, plant, equipment, labour and services for the Wind Farm as outlined above for an initial period of 5 years from the Award of Contract, with an option to extend for a further 5 years, or up to the end of design life, which ever is the longer, at the sole discretion of the Contracting Entity .
The decision on the final option will be determined either after the pre-qualification assessment or after tender evaluation/negotiation, at the Contracting Entity’s sole discretion.
This wind farm was installed in 2013.
It has 9 no. Siemens SWT93 2.3MW wind turbines.
Three options will be considered:
Option 1: Full Service & Availability Agreement including capital components.
Option 2: Service & Availability Agreement excluding capital components.
Option 3: Supply of capital components and spare parts.
The scope of service will include provision of all materials, plant, equipment, labour and services for the Wind Farm as outlined above for an initial period of 5 years from the Award of Contract, with an option to extend for a further 5 years, or up to the end of design life, which ever is the longer, at the sole discretion of the Contracting Entity .
The decision on the final option will be determined either after the pre-qualification assessment or after tender evaluation/negotiation, at the Contracting Entity’s sole discretion.
Will be set out in the Invitation to Tender.
Will be set out in the Invitation to Tender.
If the Tender is submitted by a group of suppliers, then those suppliers, if awarded the contract, shall assume such legal form by corporation, partnership or otherwise as will enable them to contract as a single entity, and assume joint and several responsibility for the contract.
Set out in the Pre-Qualification documentation..
Set out in the Pre-Qualification documentation.
Set out in the Pre-Qualification documentation.
GWM-2534
It is our intention to use the Irish Government Procurement portal (www.etenders.gov.ie) for this competition. Interested parties must register their interest on the e-Tenders website. Registration is free of charge. All information relating to and including the pre-qualification documents, any clarifications and changes will be issued/published via this portal (www.etenders.gov.ie). The contracting entity will not accept responsibility for information relayed (or not relayed) via third parties.
All such requests for participation must be received on or before (12.00GMT) on Wednesday 16 March 2016.
Responses to the pre-qualification questionnaire are required on or before (16.00GMT) on Monday 21 March 2016.
Further information on this procurement process is set out in the Pre-Qualification documentation.