Date of dispatch of this notice: 10/02/2016
Expire date: 13/04/2016
External Reference: 2016-196999
TED Reference: 2016/S 031-050792
Date of dispatch of this notice: 10/02/2016
Expire date: 13/04/2016
External Reference: 2016-196999
TED Reference: 2016/S 031-050792
15/159 - Ballyshannon Regional Water Supply Scheme Contract No.1 - Water Treatment Plant & Primary Network Design Build Operate Contract
Ireland
Irish Water is currently advancing the Ballyshannon Regional Water Supply
Scheme Design Build Operate Contract comprising the construction of an intake
structure at Lough Assaroe, pumping station, new WTP at Knader, storage
reservoir(s) including all interconnecting pipework and some trunk/distribution
mains.
The works required under the contract are to be delivered on a Contractor Design-
Build-Operate basis. The DBO contract is 24 months D-B with a 7 year Operation
and Maintenance period, with an optional add on for up to 3 years.
The planned works are necessary to ensure compliance with EU Directives, Irish
National Standards and Regulations relating to treated water for human
consumption.
The Works comprise the design and construction of infrastructure including the associated testing, commissioning and operation of the same and including the Taking-Over of the Works by the Employer. The Works can be summarised as including the following design and construction elements.
Design-Build:
• Water Intake from Lough Assaroe
• Intake Pumping Station and rising main(s)
• Provision of a new WTP at Knader (throughput tbc between 6,000 and 9,000m3/d) with wash water and sludge treatment facilities.
• Rising main(s) to Coolcholly Reservoir (approx. 1.2km)
• Coolcholly Reservoir (Phase 1 volume approx. 2,000m3, to facilitate a Phase 2 capacity of a further 2,000m3)
• Gravity mains to Parkhill WTP site (approx. 2.3km)
• Pumping Station refurbishment at Parkhill
• Rising Main to Kilclane – approx. 6.5km
• Kilclane Reservoir(s) (total volume 1,000m3)
• Further trunk & distribution mains
The services to be provided by the Contractor, over the Design Build period, as part of their obligation to the Works Requirements include but are not limited to the following:
• Detailed design of all aspects of the facilities as required by the scheme in accordance with the Works Requirements
• Preparatory works and construction facilities as required, including general clearance, construction of site and access roads and erection of security fencing
• Construction of all required structures including tanks, foundation slabs, buildings etc. and including any necessary piling, rock anchoring or other construction techniques
• Construction of the pipelines in accordance with the particular Works Requirements
• Provision of all ancillary facilities required to ensure a fully functional facility
• Provision of appropriate and sensitive landscaping at the project sites.
• Archaeology, Ecology Surveys & Monitoring during construction.
Operation Service:
• Operation Service of the works, from the intake to the outlet of the works, for an initial period of up to 7 years with the option to extend for a further period of up to 3 years at the sole discretion of the Contracting Entity.
• The Operation Service of the works will include the operation and maintenance of the water treatment plants together with associated works and will include the operation of the raw water intake and pumping facilities and the treated water into the supply network. Full details will be provided in the ITT.
An option to extend the operating period for 36 months.
Requests to participate may be submitted by single entities or by groups of service providers. A group will not be required to convert into a specific legal form in order to submit a request to participate, but may if Ervia considers it necessary to ensure that the contract is carried out to its satisfaction, be required to do so prior to award of the contract. Ervia also reserves the right to contract with each member of the group on the basis of joint and several liability, or with one member of the group as a main contractor with a number of sub-contractors or on any other basis as Ervia considers appropriate.
If any of the conditions set out in Regulation 53(1) of The European Communities (Award of Public Authorities Contract) Regulations apply to the applicant, the applicant will be excluded from the competition.
A full description of candidates’ required economics and financial capacity will be set out in the Pre-Qualification Questionnaire.
A full description of candidates’ required technical capacity will be set out in the Pre-Qualification Questionnaire.
15/159
Gaeilge
A pre-qualification questionnaire will be issued to all candidates who respond to this notice. Expressions of interest should be addressed in writing and sent via email for the attention of The Shared Services Procurement Manager to tenders@ervia.ie
The Questionnaire will cover the financial, economic and technical capacity of candidates. The questionnaire must be completed and returned to the address in I.1. above not later than 12.00hrs Tuesday 15th March 2016. The responses will be used to assist in drawing up a tender list. This process may also include interviews with candidates. The contracting entity will not be responsible for any costs, charges or expenses incurred by candidates or tenderers relating to this contract award procedure.
To receive more information about this tender, including any amendments and/or clarifications and to request any clarifications and/or to respond to this tender, you must register to this tender by email to tenders@ervia.ie
Interested parties are referred to Statutory Instrument 131 of 2010, European Communities (Award of Contracts by Utility Undertaking) (Review Procedures) Regulations 2010 (and in particular Regulation 7 and 10(2).