Date of dispatch of this notice: 21/09/2015
Expire date: 04/11/2015
External Reference: 2015-726973
TED Reference: 2015/S 186-337492
Date of dispatch of this notice: 21/09/2015
Expire date: 04/11/2015
External Reference: 2015-726973
TED Reference: 2015/S 186-337492
Inistioge Water Supply Scheme
South East Region
The proposed works will include the upgrade of the supply to Grennan WTP with
the installation of a new borehole to supplement the existing boreholes, an
upgrade to Grennan WTP, installation of 17.62 Km of watermain from Grennan to
the existing reservoir at Ballygub, Inistioge, installation of a new reservoir at
Kilmacshane, Inistioge, installation of a booster pumping station at Kilcross,
Inistioge and decommissioning of the existing intake and treatment plant at
Ballygub WTP, together with associated ancillary works.
The works to be undertaken under this Contract include the following:
o The design, construction and commissioning of a new trunk and rising mains (approximate length 17.6km) and associated infrastructure
o Watermain tie-ins
o Installation and commissioning of a new borehole in the townland of Grennan
o Installation of 4 new flow meter chambers
o Installation of a 1300m3 new reservoir adjacent to an existing reservoir in the townland of Grennan.
o Installation of a new Ultra Violet treatment kiosk adjacent to the existing building at Grennan
o Upgrading of the existing chlorine dosing treatment system in an existing building at Grennan reservoir.
o Installation of a new 560m3 reservoir in the townland of Kilmacshane, Inistioge.
o Installation of Kilcross booster pumping station kiosk complete with duty/assist/standby pumps and associated pipework and control equipment
o Decommissioning of existing fittings that serve no purpose after all works have been commissioned.
o Decommissioning of existing Ballygub water treatment plant once the alternative source has been commissioned.
o Upgrading of the existing booster pumping station in an existing structure at Woodstock Pumping Station, Inistioge.
o Pumping of watermains where necessary to maintain the water distribution system during construction and commissioning works.
o Connection of proposed watermain to existing network at various locations as shown on the PS Drawings.
o Installation of watermains using both open trench and No-Dig techniques where indicated.
o Crossing of services including bridges, culverts and landrains at locations throughout the works.
o Crossing of River Nore at Inistioge Village by No-Dig technique as specified in the Natura Impact Statement
Further details of the scope of works are included in the Pre-Qualification Questionnaire.
As per contract documents.
As per contract documents
Requests to participate may be submitted by single entities or by groups of service providers. A group will not be required to convert into a specific legal form in order to submit a request to participate, but may if Ervia considers it necessary to ensure that the contract is carried out to its satisfaction, be required to do so prior to award of the contract. Ervia also reserves the right to contract with each member of the group on the basis of joint and several liability, or with one member of the group as a main contractor with a number of sub-contractors or on any other basis as Ervia considers appropriate.
If any of the conditions set out in Regulation 53(1) of The European Communities (Award of Public Authorities Contract) Regulations apply to the applicant, the applicant will be excluded from the competition.
A full description of candidates’ required economics and financial capacity will be set out in the Pre-Qualification Questionnaire.
A full description of candidates’ required technical capacity will be set out in the Pre-Qualification Questionnaire.
15/070
Gaeilge
A pre-qualification questionnaire will be issued to all candidates who respond to this notice. Expressions of interest should be addressed in writing and sent via email for the attention of The Shared Services Procurement Manager to tenders@ervia.ie
The Questionnaire will cover the financial, economic and technical capacity of candidates. The questionnaire must be completed and returned to the address in I.1. above not later than 17.00hrs Monday 26th October 2015. The responses will be used to assist in drawing up a tender list. This process may also include interviews with candidates. The contracting entity will not be responsible for any costs, charges or expenses incurred by candidates or tenderers relating to this contract award procedure.
To receive more information about this tender, including any amendments and/or clarifications and to request any clarifications and/or to respond to this tender, you must register to this tender by email to tenders@ervia.ie
Interested parties are referred to Statutory Instrument 131 of 2010, European Communities (Award of Contracts by Utility Undertaking) (Review Procedures) Regulations 2010 (and in particular Regulation 7 and 10(2).