N15 Blackburn Bridge - Phase 1
Co Donegal
The N15 Blackburn Bridge Phase 1 comprises the construction of approximately 2.4 kilometres of standard single carriageway which is located to the southwest of Ballybofey Town.
• On-line improvements and off –line realignment of national road to the standard of Type 1 single carriageway (S2);
• Realignment of 2 single carriageway local roads;
• 1no. Bridge Structure, together with all other Structures necessary as part of the Design and the Works, including 3 no. culverts;
• Various earthworks in areas of very soft ground;
• Minor priority junctions, including various direct accesses;
• Various chambers and ducting Works, including those suitable for use by the authorities, utilities and service providers and private utility services;
• Watermain diversions;
• Various landscape, environmental and mitigation Works;
• Various culverting and re-alignment of river streams and the provision of drainage outfalls;
• Various fencing, safety barrier systems and drainage Works;
• Various signing and road marking Works;
• Various Works including diversions of the assets of the authorities, utility and service providers and private utility services;
Various site clearance works, including removal of Japanses Knotweed
• Various accommodation Works including accesses to properties and lands; and
•Various ancillary Works.
The N15 Blackburn Bridge Phase 1 comprises the construction of approximately 2.4 kilometres of standard single carriageway which is located to the southwest of Ballybofey Town.
• On-line improvements and off –line realignment of national road to the standard of Type 1 single carriageway (S2);
• Realignment of 2 single carriageway local roads;
• 1no. Bridge Structure, together with all other Structures necessary as part of the Design and the Works, including 3 no. culverts;
• Various earthworks in areas of very soft ground;
• Minor priority junctions, including various direct accesses;
• Various chambers and ducting Works, including those suitable for use by the authorities, utilities and service providers and private utility services;
• Watermain diversions;
• Various landscape, environmental and mitigation Works;
• Various culverting and re-alignment of river streams and the provision of drainage outfalls;
• Various fencing, safety barrier systems and drainage Works;
• Various signing and road marking Works;
• Various Works including diversions of the assets of the authorities, utility and service providers and private utility services;
Various site clearance works, including removal of Japanses Knotweed
• Various accommodation Works including accesses to properties and lands; and
•Various ancillary Works.