Kingswood - 1,000 pupil post primary school

Works

10/11/2015 17:00:00

45214220-8  Secondary school construction work


Department of Education
Marlborough Street
Dublin 1
Dublin
Ireland
View profile

Hugh Levins
http://www.education.ie

Published notices
Contract Notice (eTenders) 02/10/2015 14:10
Contract notice (TED (v208)) 02/10/2015 13:40
Contract Award Notice (eTenders)
Contract award notice (TED (v209)) 28/08/2017 09:40
Lots
1,000 pupil post primary school

1,000 pupil post primary school with SENS unit on green field site. The school is generally two-storey and is 10,496 sq.m GFA. The works will include the provision of temporary accommodation for the duration of the works and the removal of same on completion. The project includes all associated site works including new football pitch in location of the temporary accommodation