Removal of wall, insertion of steel beam, new flooring, door ope and all associated site works. Note: The works are to be carried out during the school holidays when the school will be closed. A management plan is to be prepared and discussed with the School Principal regarding controlled access to the site and relevant areas of the building.
Works
04/07/2022 16:00:00
45000000-7 Construction work
Scoil Mhuire na mBuachailli (Castleblayney)
Dublin Road
Co.Monaghan
Castleblayney
Ireland
View profile
Declan Smyth
| Notice | Date of dispatch |
|---|---|
| Contract Notice (eTenders) | 22/06/2022 16:00 |