Presentation Primary SW 2014 - School Heating system replacement mechanical SW2014 Scheme

The RFT has ended, you cannot answer the invitation.

The mechanical contractor for this project will take responsibility as the main contractor and PSCS responsible for all associated works. Demolition of heating system & removal from site, and removal of the existing oil storage tank. New boiler house installation including gas fired boiler, pumps, controls, all pipe work. Repiping and fitting of new radiators to 16 classrooms and anciliary areas.

Works

02/07/2014 12:00:00

45315000-8  Electrical installation work of heating and other electrical building-equipment
45331100-7  Central-heating installation work
45331110-0  Boiler installation work
45351000-2  Mechanical engineering installation works
71334000-8  Mechanical and electrical engineering services


Overy+Assocoiates
Unit 5a, Gurtnafleur Business Park
Co Tipperary
Clonmel
Ireland
View profile

Paul Overy
http://www.overy.ie

Published notices
Contract Notice (eTenders) 24/06/2014 23:10
Lots
Heating system replacement under summer works
Additional information:
Documents Documents
Close