Project consists of complete replacement of LPHW heating system affecting three wings of the school (referred to as the 40's, 50's & 60's wings). The older 1965 3 storey building was upgraded under the SWS 2014 scheme and operates from a separate boiler house. Therefore, the replacement of the boiler and upgrading of boiler house 2 would also be included as part of the project. For a detailed description of the extent of the work involved, please see page 1 of consultant's report on SWS 2017 application, copy of which is attached as a separate document.
Services
27/06/2017 12:00:00
71000000-8 Architectural, construction, engineering and inspection services
71315210-4 Building services consultancy services
St. Paul's Secondary School (Greenhills)
Limekiln Lane, Greenhills
Co.Dublin
Dublin 12
Ireland
View profile
Grainne Hartigan
| Notice | Date of dispatch |
|---|---|
| Contract Notice (eTenders) | 16/06/2017 14:00 |