Irish Water plan to undertake the development of 2 No. Water Treatment Plants (WTP) together with associated works as part of the Kerry Central Regional Water Supply Project (KCRWSP) and the North East Roscommon Regional Water Supply Project (NERRWSP). The planned works are necessary to ensure compliance with EU Directives, Irish National Standards and Regulations relating to treated water for human consumption. The works are divided into Lots. It is intended that each Lot will be implemented under a Design, Build and Operate (“DBO”) Contract.
Works
17/11/2014 17:00:00
45232430-5 Water-treatment work
45240000-1 Construction work for water projects
45252126-7 Drinking-water treatment plant construction work
45252140-1 Sludge-dewatering plant construction work
45315100-9 Electrical engineering installation works
45351000-2 Mechanical engineering installation works
65130000-3 Operation of water supplies
Gas Networks Ireland
Gasworks Road
Cork
Cork
Ireland
View profile
Janet Swayne
http://www.gasnetworks.ie
| Notice | Date of dispatch |
|---|---|
| Contract Notice (eTenders) | 10/10/2014 16:40 |
| Contract notice - utilities (TED (v208)) | 10/10/2014 14:01 |
•Upgrade of 2 No. existing Intakes •New Raw Water Storage Tank •New Low Lift Pumps •Refurbishment and upgrade of existing plant building and assets •New Water Treatment Works with an ultimate capacity of 51,000m3/d •New Clear Water Storage Tank •New High Lift Pumping facility •Associated raw and treated water pipelines •Rising Main Facilitation Works and diversions •Provision of a SCADA and telemetry system •Associated Siteworks and Landscaping Works
A pre-qualification questionnaire will be issued to all candidates who forward an Expression of interest and send via email for the attention of The Shared Services Procurement Manager to jswayne@bge.ie The questionnaire must be completed and returned to the address in I.1. above not later than 17.00hrs Monday 17th Novemeber 2014. PLEASE DO NOT REGISTER ON ETENDERS AS YOU WILL NOT RECEIVE ANY DOCUMENTATION.
•New raw water intake works and pumping station at Grange Lough •New water treatment works on a green field site with an ultimate capacity of 6,000m3/d •Treated water pumping station •Associated raw and treated water pipelines •Provision of a SCADA and telemetry system •Associated Siteworks and Landscaping Works •Operation and maintenance of the works
A pre-qualification questionnaire will be issued to all candidates who forward an Expression of interest and send via email for the attention of The Shared Services Procurement Manager to jswayne@bge.ie The questionnaire must be completed and returned to the address in I.1. above not later than 17.00hrs Monday 17th November 2014. PLEASE DO NOT REGISTER ON ETENDERS AS YOU WILL NOT RECEIVE ANY DOCUMENTATION.