The N52 Cloghan to Billistown Phase 2 - Turin to Billistown Realignment comprises the construction of 6.0km of Type 1 Single Carriageway (S2) National Secondary road and associated works including: (1) at grade junctions and links to existing road network (2) accommodation works underpasses (3) surface water drainage infrastructure (4) utility diversions works, including ESB, Eir and Irish Water (5) road signs, road markings and road studs (6) site clearance and earthworks (7) boundary treatment works and accommodation works (8) landscaping works (9) road pavements. The contractor will be required to produce Traffic Management plans for the N52 National Secondary road and local roads. The contractor will also be appointed as the Project Supervisor Construction Stage (PSCS). The full scope of the work and obligations of the contractor are to be ascertained by reference to the contract documents as a whole.
Works
21/12/2018 16:00:00
45233100-0 Construction work for highways, roads
45233120-6 Road construction works
Westmeath County Council
Áras An Chontae, Mountstreet, N91 FH4N
Mullingar
County Westmeath
Ireland
View profile
Ambrose Clarke
http://www.westmeathcoco.ie/
Notice | Date of dispatch |
---|---|
Contract notice (TED (v209)) | 15/11/2018 18:10 |
Contract award notice (TED (v209)) | 24/04/2019 18:10 |
The N52 Cloghan to Billistown Phase 2 - Turin to Billistown Realignment comprises the construction of 6.0km of Type 1 Single Carriageway (S2) National Secondary road and associated works. The full scope of the work and obligations of the contractor are to be ascertained by reference to the contract documents as a whole.
As stated in the procurement documents available for download