6974 - EMU Main Alternator and Locomotive Main Generator Overhauls

The RFT has ended, you cannot answer the invitation.

This is a call to competition by IE for the procurement of EMU Main Alternator and Locomotive Main Generator Overhauls (the “Contract”).

 

Lot 1: Overhaul of GEC Type G781/DW M/A set

·        There is a total of 28no overhauls to be carried out over a 18-24 month period, these overhauls are to include new Gino resistors that will be provided by Iarnród Éireann.

·        In addition to this, a further 9no M/A sets, already overhauled, are to have Gino resistors fitted over a two month period after the main overhauls.

·        A requirement of a break/fix casualty repair to be in place until July 2021.

 

Lot 2: 201 Class locomotive AR8PHEH / Main Generator / CA6B Alternator

·        There is a requirement to have 12 (4 per annum) overhauls done on the main generators.

 

·        A requirement of a break/fix casualty repair to be in place until July 2021.